#GiantOilRig – A giant oil-rig the Blackford Dolphin, which was initially only supposed to be in Belfast for a six-week refurbishment, is to finally depart Belfast today after six months dominating the city's skyline.
As previously reported on Afloat.ie, the platform is one of the world's biggest such structures, the 260ft rig, that sailed into the harbour before Christmas, will be heading back to Norway at a snail's pace after her multi-million pound refit at Harland & Wolff, which employed some 400 workers on the project.
The contract price for the work is thought to be over £100m.
While the initial work schedule was only supposed to take 60 days, following the discovery of some structural defects on the rig when it came into the world's largest dock, the structure underwent months more repairs by welders, electricians, painters and engineers from the UK, Poland and Portugal.