Marine Minister Charlie McConalogue today (Thursday 2 March) officially named the new €10m ‘Fishing Pier’ at Howth Fishery Harbour Centre, one of the six State-owned Fishery Harbour Centres.

The works comprised the construction of 134 metres of new quay wall, dredging, stabilisation and infill of subsea material which covers a greatly enlarged area of 6,500 sqm.

The additional berthing space created relieves vessel congestion issues and enables greater segregation between the activities of fishing vessels and the marine tourism and leisure activities which are mainly concentrated on the West Pier.

Works on the site commenced in October 2020 and were completed in April 2022 at a cost of €10 million.

Howth's new fishing pier - The works comprised the construction of 134 metres of new quay wall, dredging, stabilisation and infill of subsea material which covers a greatly enlarged area of 6,500 sqmHowth's new fishing pier - The works comprised the construction of 134 metres of new quay wall, dredging, stabilisation and infill of subsea material which covers a greatly enlarged area

This major redevelopment project was funded through the Department of Agriculture, Food and the Marine’s Fishery Harbour and Coastal Infrastructure Development Programme.

Officially opening ‘The Fishing Pier’, the minister said: “It is an integral part of my department’s overall strategy to provide dedicated, stand-alone fit for purpose facilities for the fishing industry in Howth.

“The newly redeveloped ‘Fishing Pier’ facilitated the moving of vessels from the West Pier onto this redeveloped pier. I must also acknowledge our main contractor, John Sisk, and consulting engineer Malachy Walsh and Partners who overcame COVID-19 restrictions and supply chain delays to deliver a first-class structure.”

Bird’s eye view of the new Fishing Pier at HowthBird’s eye view of the new Fishing Pier at Howth

In 2021, almost 90% of all fish landed into Ireland was into the six State-owned Fishery Harbour Centres. At Howth, these landings were valued at c.€12.9 million.

Minister McConalogue noted: “The six Fishery Harbour Centres are critical infrastructure for our seafood industry. By attracting increased fish landings, we will deliver the raw materials to drive and maximise the opportunities for primary and secondary processing and ensure a strong Irish seafood processing industry. The importance of these primary and secondary food production activities is reflected in the Government’s Food Vision 2030 policy“.

The new pier adds extensive and much-needed quay space of 6,500m2 in a seasonally very busy harbourThe new pier adds extensive and much-needed quay space of 6,500m2 in a seasonally very busy harbour

HOWTH DREDGING PLANS

The Department of Agriculture, Food and the Marine says it has plans for further significant investment with a dredging and reclamation project for Howth Fishery Harbour Centre and planning permission for this project is currently under consideration by An Bord Pleanála.

After unveiling the plaque, Minister McConalogue said: “In addition to the fisheries and seafood production industries, the Fishery Harbour Centres are accommodating an ever-increasing amount of diverse marine commercial business, including commercial cargo traffic, cruise liners, restaurants and other leisure, tourism, and social activities.

“All of these activities complement the critical economic activity generated by our fishing industry and help to maintain the vitality of these coastal communities.”

Published in Fishing

The Department of Agriculture, Food and the Marine invites suitably qualified contractors to submit a tender package to construct up to two reinforced concrete boatyard repair bays within the existing DAFM Boatyard located on the West Pier of Howth Fishery Harbour Centre.

The repair bays will be around 500 sqm each, with works to include surfacing, installation of draining pipework, gullies and manholes (of a depth not greater than 2m) and more.

The successful contractor will also be expected to excavate and dispose of existing life-expired asphalt surfacing off-site at a licensed facility.

This tender award is expected in late May or early June with works to commence in June or July, and is awarded subject to available funding.

The RFT is in one lot and can be viewed on the eTenders website under reference 210774. The deadline for responses to this tender is noon on Wednesday 4 May.

Published in Irish Harbours

The Department of Agriculture, Food and the Marine is inviting tenders from suitably qualified contractors to carry out various upgrade works on the Arsenal Building on Howth Harbour’s West Pier.

The building currently serves as the fishermen’s toilet and shower unit at Howth Fishery Harbour Centre in north Co Dublin.

Works required include roofing, stonework cleaning and pointing as well as general repairs and upgrades such as installing new doors and windows.

Tenders are to be submitted in one lot. The request for tender (RFT) is in a single lots and can be viewed on the eTenders website under reference 196560.

Published in Irish Harbours
Tagged under

A new Notice to Mariners (2562/21) provides information on reduced depths at the entrance to Howth Harbour and Marina and was issued today (14/06/2021) by the UK Hydrographic Office.

The notice was circulated by Harbour Master Harold McLoughlin at the Howth Fishery Harbour Centre.

Download the full notices below as PDF files

Reduced depths at the entrance to Howth Harbour and MarinaReduced depths at the entrance to Howth Harbour and Marina

Published in Howth YC
Tagged under

The Department of Agriculture, Food and the Marine is seeking tenders for the resurfacing of repair bays within its boatyard at Howth Fishery Harbour Centre in North Co Dublin.

The request for tender is divided into two lots and calls for the upgrade of the existing 520 sqm work bays at the West Pier of Howth Harbour with new drainage and a reinforced concrete surface.

The first lot is to be awarded to a suitable contractor for construction in summer 2021. A second lot may be awarded subject to available funding for works later this year or early 2022.

For more details on the tender see the eTenders website HERE.

Published in Irish Harbours
Tagged under

Dublin Bay Old Gaffers Association invites you to join their next Zoom session, which will be on The Building of Howth Harbour and presented by Rob Goodbody on Thursday, 8th April at 20:00hrs.

The present Howth Harbour celebrated its Bicentenary last year. Rob Goodbody will explain how the small harbour at Howth, which had existed for centuries primarily for small fishing boats, underwent huge development during the early decades of the Nineteenth Century following the Act of Union, and the transfer of power from Dublin to London.

Howth Harbour became the mail packet station for the Dublin-London route. But with the advent of larger steamships, the harbour became too small and the mails were transferred to the newer larger harbour at Kingstown, leaving Howth to revert back to a fishing port.

Rob Goodbody trained in geography, planning and building conservation, and has a great interest in local history and industrial heritage. He worked as a planner for local authorities in London and Dublin from 1974 to 2003. Since then, Rob has specialised in historic building conservation and has published a number of books, including The Metals - from Dalkey to Dun Laoghaire about the construction of Dun Laoghaire Harbour, and he also co-authored Dublin Bay - Nature & History.

Please come early to be sure of getting a good seat.

DBOGA Fundraising for HOWTH RNLI: Pre-Covid, listened to talks together at Poolbeg while passing the Yellow Welly around for a €5 donation. In Zoom Land we can't
do that but the RNLI urgently needs funds.

Please click on: www.justgiving.com/fundraising/DBOGAHowthLifeboat to contribute your €5. DBOGA are well on the way to our target of €4,000. Thank you!

The details of this Zoom meeting are:

Topic: Rob GoodbodyTalk
• Time: April 8th 2021, at 20.00hrs

Link to join the meeting: https://us02web.zoom.us/j/85300865136

Meeting ID: 853 0086 5136

Howth Harbour today – among many changes, the sunshine allocation has been significantly increasedHowth Harbour today – among many changes, the sunshine allocation has been significantly increased

Published in Howth YC
Tagged under

The Department of Agriculture, Food and the Marine (DAFM), the harbour authority for Howth Harbour Fishery Centre in North County Dublin, is proposing to dredge seabed material from within the harbour to provide better water access to the fishing, leisure, and RNLI craft using the harbour.

Silting of the harbour and the subsequent dredging conversation has been an ever-present challenge for the harbour over the past two decades. 

It is proposed to reuse the material to create an area for the public realm on the west side of the West Pier.

The volume of material to be removed is approximately 240,000m3, and the area to be created is approximately 4.8ha.

The reclaimed area would be used for public realm, water access for leisure users, car parking and hard standing areas that can be used for storage areas for existing harbour leisure users and the harbour authority. In the future, some of the area created may be converted to light industrial/ commercial use to support harbour operations. Such future use is not part of the proposed development being considered at present.

Howth Harbour in North County DublinHowth Harbour in North County Dublin

The harbour was upgraded in the 1980s when the Syncrolift, the berthage face along the west pier, the present middle pier, the internal breakwater, and the marina area were constructed.

Enhancement of water depths within the harbour area is now required to maintain safe access to the harbour during any tide state. This is necessary because of increased fishing vessel sizes, siltation, and a desire to improve the usable water area. Lack of sufficient water depths due to siltation in the vicinity of the public and RNLI slipways is resulting in restricted access to the water for the public and RNLI rescue craft at low tide.

To this end, the DAFM are preparing a planning application, EIAR and NIS for a proposed dredging and reclamation project at Howth Harbour FHC.

While a town hall public consultation exercise would normally be undertaken to inform the preparation of a planning application with an EIAR, because of COVID restrictions, this public consultation exercise is being undertaken virtually.

Howth harbour dredging plansDetails of the West Pier's proposed design, utilising the spoil from the dredging

Proposed Howth Harbour Development

The proposed development will be the subject of a planning application by the Department of Agriculture, Food and the Marine and relates to the following main elements:

  • Dredging of the harbour and reclamation of land on the west side of the West Pier using treated dredge material;
  • The dredge material will be treated using soil stabilisation techniques prior to placement in the reclamation area. This will improve the strength of soil, bind in contaminants and minimise the potential for leachate;
  • Coastal protection works to the perimeter of the reclaimed area;
  • Landscaping on the reclaimed area and construction of footways, roadways and parking areas;
  • Construction of viewing points and a slipway for access to the water;
  • Construction of storage areas for harbour activities;
  • Provision of necessary services.

If you would like to submit your comments or feedback, you can do so at:

[email protected]

Comments must be submitted before 2300hrs (11pm) Friday 09 April 2021

Download the full proposal below (7mb)

Published in Dredging
Tagged under

"Getting the builders in" is a challenging prospect on land at the best of times. Add in the sea, and it's then a challenge-plus. Thus when you're working on and in the waterfront to implement a project within a busy fishing/sailing harbour which has found itself becoming something of a cult tourism magnet, the problems are magnified tenfold for contractors and harbour users alike.

Certainly, this is the prospect at Howth, where this week Sisk the Builders will be starting to move in to set up a new operational site on the Middle Pier. This will – in just 13 months, it is hoped - provide a completely new 135 metres of proper quay wall along the currently rock-armoured west side of the Middle Pier, with dredged material from the new "long berth" being deposited in a revetment-retained infill on the Middle Pier's East Side, thereby providing much-needed extra shore space for vehicles serving the boats using the new berths.

Part of Howth's attraction for visitors is the colourful but often very crowded scene along the main fishing boat area on the West Pier. It's entertaining to be feasting off seafood at one of the many characterful restaurants along the pier, as forklifts with fishing gear go buzzing closely past. And every so often, a seemingly enormous fishing boat makes her stately way across the quay in slow style on the Syncrolift trolleys to receive the attentions of Johnny Leonard and his skilled staff in the shipyard. There's never a dull moment. But there are times when it's all just too much of a good thing. A safety valve of alternative berthing and extra shoreside space was becoming urgently needed.

Howth's Fish Dock may provide a colourful setting for a quayside array of characterful seafood restaurants along the West PierHowth's Fish Dock may provide a colourful setting for a quayside array of characterful seafood restaurants along the West Pier, but extra berthing space is urgently needed. Photo: W M Nixon

Down along the west side of the Middle Pier was the only option. This would be simple enough if everyone was game to close off substantial parts of the harbour to let the contractors have a free run at the job. But it says everything about the spirit of Howth that this doesn't seem to have occurred to anyone. From the beginning, the assumption was that virtually all of the harbour's activities could continue with as little interruption as possible, and Harbour Master Harry McLoughlin and Howth Yacht Cub Commodore Ian Byrne, together with representatives of other interests, set themselves the task of facilitating the contractors while keeping the floating show on the road.

As Ian Byrne became our "Sailor of the Month" back in May for deciphering the multiple rules for exiting the first Covid lockdown in a way which was comprehensible to all sailors, he was ideal to speak for the consumers, while Harry McLoughlin - a widely-experienced harbour master who has a real vision for Howth - ably filled the role as the human face of officialdom. Between themselves and the contractors, they worked out a viable scheme despite having to include extra elements made necessary by the space requirements of COVID-19

Site plan showing (red line) the agreed limits of the boundary of the works. This will enable much of the harbour – including the public slipway beside the Lifeboat StationSite plan showing (red line) the agreed limits of the boundary of the works. This will enable much of the harbour – including the public slipway beside the Lifeboat Station – to continue to function, but inevitably there will be some reduction in car parking spaces.

Of course, those who know Howth well appreciate that while this new project will – if all goes according to plan - give the fishing fleet a very welcome and useful Christmas present at the end of 2021, it is just the beginning of a process in which the long-overdue dredging of the harbour – more needed in some parts then in others – is steadily moving up the agenda.

But if this scheme goes according to plan in a spirit of harmony, it will, in turn, create the atmosphere in which other mutually beneficial works can be undertaken with an attitude of realism and a mood of mutual respect. And if by some happy chance the pandemic subsides and visitors are allowed back to Howth in their previous numbers next Spring, well, the fact that there's an interesting bit of maritime contracting work underway will give them something extra to look at, for the main attraction of Howth Harbour seems to be that people on holiday enjoy nothing more than watching other people doing unusual work…

Howth_middle_pier_from_northBy the beginning of November (COVID permitting) this end section of Howth's Middle Pier will be a hive of activity with the rock armour on the Fish Dockside being converted into a quay wall.

Published in Howth YC
Tagged under

The Department of Agriculture, Food and the Marine has updated local Fingal councillors on its proposals for the dredging of Howth Harbour.

On his Facebook page, Cllr Cian O’Callaghan says the meeting with the department and the Howth Harbour Master on Wednesday (6 March) detailed a plan to dredge five key areas of the harbour, namely:

  • The fishing trawler basin between the West Pier and Middle Pier
  • The approach channel at the mouth of the harbour
  • The marina used by Howth Yacht Club
  • The approach channel to the marina
  • The outer moorings area which is used by the Howth Sailing and Boat Club

This would result in the extraction of 225,000 cubic metres of silt, the equivalent of up to 30,000 lorry loads, says Cllr O’Callaghan.

The detailed plan follows testing of material extracted from the harbour which confirms that while is it contaminated by general harbour activity, it is not considered hazardous.

It is being proposed that the spoil be treated and used to create a 100-metre-wide infill area along the west side of the present West Pier. Plans for the use of this new space have not yet been decided but it is expected there will be a relevant public consultation by year’s end.

Four months ago the tender period closed for engineering services related to these long-awaited dreading works in the North Co Dublin harbour.

Published in Dredging
Tagged under

#NavalService -  Fishing boats, both Irish-registered have been detained in the Irish Sea for alleged breaches of fishing rules.

It was part of an overnight operation The Irish Examiner writes by the Naval Service patrol vessel LE Eithne when officers boarded the two boats.

The vessels are being escorted to Howth Harbour in Co.Dublin and will then be handed over to Gardaí.

It brings to seven the number of boats detained by the Naval Service so far this year.

Published in Navy
Page 1 of 3

Ireland's Offshore Renewable Energy

Because of Ireland's location at the Atlantic edge of the EU, it has more offshore energy potential than most other countries in Europe. The conditions are suitable for the development of the full range of current offshore renewable energy technologies.

Offshore Renewable Energy FAQs

Offshore renewable energy draws on the natural energy provided by wind, wave and tide to convert it into electricity for industry and domestic consumption.

Offshore wind is the most advanced technology, using fixed wind turbines in coastal areas, while floating wind is a developing technology more suited to deeper water. In 2018, offshore wind provided a tiny fraction of global electricity supply, but it is set to expand strongly in the coming decades into a USD 1 trillion business, according to the International Energy Agency (IEA). It says that turbines are growing in size and in power capacity, which in turn is "delivering major performance and cost improvements for offshore wind farms".

The global offshore wind market grew nearly 30% per year between 2010 and 2018, according to the IEA, due to rapid technology improvements, It calculated that about 150 new offshore wind projects are in active development around the world. Europe in particular has fostered the technology's development, led by Britain, Germany and Denmark, but China added more capacity than any other country in 2018.

A report for the Irish Wind Energy Assocation (IWEA) by the Carbon Trust – a British government-backed limited company established to accelerate Britain's move to a low carbon economy - says there are currently 14 fixed-bottom wind energy projects, four floating wind projects and one project that has yet to choose a technology at some stage of development in Irish waters. Some of these projects are aiming to build before 2030 to contribute to the 5GW target set by the Irish government, and others are expected to build after 2030. These projects have to secure planning permission, obtain a grid connection and also be successful in a competitive auction in the Renewable Electricity Support Scheme (RESS).

The electricity generated by each turbine is collected by an offshore electricity substation located within the wind farm. Seabed cables connect the offshore substation to an onshore substation on the coast. These cables transport the electricity to land from where it will be used to power homes, farms and businesses around Ireland. The offshore developer works with EirGrid, which operates the national grid, to identify how best to do this and where exactly on the grid the project should connect.

The new Marine Planning and Development Management Bill will create a new streamlined system for planning permission for activity or infrastructure in Irish waters or on the seabed, including offshore wind farms. It is due to be published before the end of 2020 and enacted in 2021.

There are a number of companies aiming to develop offshore wind energy off the Irish coast and some of the larger ones would be ESB, SSE Renewables, Energia, Statkraft and RWE.

There are a number of companies aiming to develop offshore wind energy off the Irish coast and some of the larger ones would be ESB, SSE Renewables, Energia, Statkraft and RWE. Is there scope for community involvement in offshore wind? The IWEA says that from the early stages of a project, the wind farm developer "should be engaging with the local community to inform them about the project, answer their questions and listen to their concerns". It says this provides the community with "the opportunity to work with the developer to help shape the final layout and design of the project". Listening to fishing industry concerns, and how fishermen may be affected by survey works, construction and eventual operation of a project is "of particular concern to developers", the IWEA says. It says there will also be a community benefit fund put in place for each project. It says the final details of this will be addressed in the design of the RESS (see below) for offshore wind but it has the potential to be "tens of millions of euro over the 15 years of the RESS contract". The Government is also considering the possibility that communities will be enabled to invest in offshore wind farms though there is "no clarity yet on how this would work", the IWEA says.

Based on current plans, it would amount to around 12 GW of offshore wind energy. However, the IWEA points out that is unlikely that all of the projects planned will be completed. The industry says there is even more significant potential for floating offshore wind off Ireland's west coast and the Programme for Government contains a commitment to develop a long-term plan for at least 30 GW of floating offshore wind in our deeper waters.

There are many different models of turbines. The larger a turbine, the more efficient it is in producing electricity at a good price. In choosing a turbine model the developer will be conscious of this ,but also has to be aware the impact of the turbine on the environment, marine life, biodiversity and visual impact. As a broad rule an offshore wind turbine will have a tip-height of between 165m and 215m tall. However, turbine technology is evolving at a rapid rate with larger more efficient turbines anticipated on the market in the coming years.

 

The Renewable Electricity Support Scheme is designed to support the development of renewable energy projects in Ireland. Under the scheme wind farms and solar farms compete against each other in an auction with the projects which offer power at the lowest price awarded contracts. These contracts provide them with a guaranteed price for their power for 15 years. If they obtain a better price for their electricity on the wholesale market they must return the difference to the consumer.

Yes. The first auction for offshore renewable energy projects is expected to take place in late 2021.

Cost is one difference, and technology is another. Floating wind farm technology is relatively new, but allows use of deeper water. Ireland's 50-metre contour line is the limit for traditional bottom-fixed wind farms, and it is also very close to population centres, which makes visibility of large turbines an issue - hence the attraction of floating structures Do offshore wind farms pose a navigational hazard to shipping? Inshore fishermen do have valid concerns. One of the first steps in identifying a site as a potential location for an offshore wind farm is to identify and assess the level of existing marine activity in the area and this particularly includes shipping. The National Marine Planning Framework aims to create, for the first time, a plan to balance the various kinds of offshore activity with the protection of the Irish marine environment. This is expected to be published before the end of 2020, and will set out clearly where is suitable for offshore renewable energy development and where it is not - due, for example, to shipping movements and safe navigation.

YEnvironmental organisations are concerned about the impact of turbines on bird populations, particularly migrating birds. A Danish scientific study published in 2019 found evidence that larger birds were tending to avoid turbine blades, but said it didn't have sufficient evidence for smaller birds – and cautioned that the cumulative effect of farms could still have an impact on bird movements. A full environmental impact assessment has to be carried out before a developer can apply for planning permission to develop an offshore wind farm. This would include desk-based studies as well as extensive surveys of the population and movements of birds and marine mammals, as well as fish and seabed habitats. If a potential environmental impact is identified the developer must, as part of the planning application, show how the project will be designed in such a way as to avoid the impact or to mitigate against it.

A typical 500 MW offshore wind farm would require an operations and maintenance base which would be on the nearby coast. Such a project would generally create between 80-100 fulltime jobs, according to the IWEA. There would also be a substantial increase to in-direct employment and associated socio-economic benefit to the surrounding area where the operation and maintenance hub is located.

The recent Carbon Trust report for the IWEA, entitled Harnessing our potential, identified significant skills shortages for offshore wind in Ireland across the areas of engineering financial services and logistics. The IWEA says that as Ireland is a relatively new entrant to the offshore wind market, there are "opportunities to develop and implement strategies to address the skills shortages for delivering offshore wind and for Ireland to be a net exporter of human capital and skills to the highly competitive global offshore wind supply chain". Offshore wind requires a diverse workforce with jobs in both transferable (for example from the oil and gas sector) and specialist disciplines across apprenticeships and higher education. IWEA have a training network called the Green Tech Skillnet that facilitates training and networking opportunities in the renewable energy sector.

It is expected that developing the 3.5 GW of offshore wind energy identified in the Government's Climate Action Plan would create around 2,500 jobs in construction and development and around 700 permanent operations and maintenance jobs. The Programme for Government published in 2020 has an enhanced target of 5 GW of offshore wind which would create even more employment. The industry says that in the initial stages, the development of offshore wind energy would create employment in conducting environmental surveys, community engagement and development applications for planning. As a site moves to construction, people with backgrounds in various types of engineering, marine construction and marine transport would be recruited. Once the site is up and running , a project requires a team of turbine technicians, engineers and administrators to ensure the wind farm is fully and properly maintained, as well as crew for the crew transfer vessels transporting workers from shore to the turbines.

The IEA says that today's offshore wind market "doesn't even come close to tapping the full potential – with high-quality resources available in most major markets". It estimates that offshore wind has the potential to generate more than 420 000 Terawatt hours per year (TWh/yr) worldwide – as in more than 18 times the current global electricity demand. One Terawatt is 114 megawatts, and to put it in context, Scotland it has a population a little over 5 million and requires 25 TWh/yr of electrical energy.

Not as advanced as wind, with anchoring a big challenge – given that the most effective wave energy has to be in the most energetic locations, such as the Irish west coast. Britain, Ireland and Portugal are regarded as most advanced in developing wave energy technology. The prize is significant, the industry says, as there are forecasts that varying between 4000TWh/yr to 29500TWh/yr. Europe consumes around 3000TWh/year.

The industry has two main umbrella organisations – the Irish Wind Energy Association, which represents both onshore and offshore wind, and the Marine Renewables Industry Association, which focuses on all types of renewable in the marine environment.

©Afloat 2020