Waterways Ireland advises masters of vessels on the Shannon Navigation that in-river works for the construction of the Killaloe Bypass upper bridge superstructure are progressing as planned and will continue until October 2024.

As previously reported on Afloat.ie, the bridge is being constructed around 1km downstream of the current Killaloe–Ballina bridge.

A buoyed navigational channel continues to be provided for 100 metres either side of the in-river works.

The following plant and equipment will be operating on or overhead the navigation during the upper bridge works:

  • 600t crawler crane set up on the east shore
  • Stabilising crane barge (30m x 23m x 1.88m)
  • 100t crawler crane
  • Tugboat/pusher boat
  • Dumb barge (23m x 9m) and mobile elevated work platforms
  • Safety boat
  • Landing pontoon and gangways

From next Tuesday 2 to Friday 19 April, the final steel girders will be lifted into position in the central spans of the bridge.

This is a heavy lift operation and deemed high-risk work, requiring calm waters for operation of mobile elevated work platforms (MEWP) on barges.

Masters of vessels are requested to proceed at slow speed (5 knots, no wash) with additional caution in the vicinity of the works, and to follow the instructions of the safety boat crew as there are hazards such as bridge piers, steel piles and mooring lines to navigate.

The cross-border body for Ireland’s inland waterways thanks its customers for their cooperation in relation to these works.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on and users of the Shannon Navigation that Uisce Éireann will be installing an outfall downstream of Killaloe and Ballina from next Monday 21 August to the end of September.

A work barge will be launched from the carpark adjacent to the Waterways Ireland building in Killaloe and will operate south of the bridge adjacent to the Ballina wastewater treatment plant for the duration of the works.

The outfall will extend from the Ballina plant into the river for a distance of 90 metres.

Two temporary special markers will be installed to mark the limits of the in-river works area downstream of Killaloe and Ballina. A permanent navigation marker will be installed when the works are completed.

Masters of vessels should proceed with additional caution in the vicinity of the works, adds the cross-border body for Ireland’s inland waterways.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on the Shannon Navigation that the in-river works for the construction of the Killaloe Bypass bridge continue to progress as planned.

As previously reported on Afloat.ie, the bridge is being constructed around 1km downstream of the current Killaloe–Ballina bridge.

Three bridge piers will be constructed in the navigation by December. The first 10 piles were installed on the east side of the river by early June with 10 more on the west side by late June.

Barges and piling moved from the west side to the centre of the river in early July and will be relocated to the west side of the navigation from Monday 7 August.

The crane barge will move to the east jetty and load out precast shells on Tuesday 8 August. It is intended to lift precast concrete shells into position on Wednesday 9, Thursday 10 and Friday 11 August. This is a heavy-lift operation and deemed high-risk work, requiring calm waters.

A buoyed navigation channel is being provided for 100 metres either side of the in river works, the cross-border body for Ireland’s inland waterways adds.

Masters of vessels are requested to proceed at slow speed (5 knots, no wash) with additional caution in the vicinity of the works and to follow the instructions of the safety boat crew as there are hazards such as steel piles and mooring lines to navigate.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on the Shannon Navigation that the in-river works for the construction of the Killaloe Bypass bridge are progressing as planned.

As previously reported on Afloat.ie, the bridge is being constructed around 1km downstream of the current Killaloe–Ballina bridge.

Three bridge piers will be constructed in the navigation by December. The first 10 piles were installed on the east side of the river by early June with 10 more on the west side by last week, the cross-border body for Ireland’s inland waterways confirms.

A buoyed navigation channel is being provided for 100 metres either side of the in river works. The barges and piling rig have now moved from the west side to the centre of the river as of Tuesday 1 July.

Masters of vessels are requested to proceed at slow speed (5 knots, no wash) with additional caution in the vicinity of the works and to follow the instructions of the safety boat crew as there are hazards such as mooring lines to navigate.

Published in Inland Waterways

Tributes have been paid to 19-year-old Wassiou Ayawe, who died after an incident involving a jet ski in Killaloe on Wednesday afternoon (31 May).

As RTÉ News reports, the talented footballer died after he and two teenage girls were thrown into the waters of Lough Derg after the personal watercraft they were riding flipped over near Killaloe Bridge.

It’s understood that the two girls, who were wearing lifejackets, were able to swim to safety.

Colin Becker, former president of the Inland Waterways Association of Ireland said: “Our sympathies go to the victim's family and friends.”

Published in Jetski
Tagged under

Waterways Ireland advises masters of vessels on the Shannon Navigation that the in-river works for the construction of the Killaloe Bypass bridge are progressing as planned.

As previously reported on Afloat.ie, the bridge is being constructed around 1km downstream of the current Killaloe–Ballina bridge.

Three bridge piers will be constructed in the navigation by December. The first 10 piles have now been installed on the east side of the river, the cross-border body for Ireland’s inland waterways confirms.

A buoyed navigation channel is being provided for 100 metres either side of the in river works. The barges and piling rig will be operating on the west side of the river from Thursday 1 June.

Masters of vessels are requested to proceed at slow speed (5 knots, no wash) with additional caution in the vicinity of the works and to follow the instructions of the safety boat crew as there are hazards such as mooring lines to navigate.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on the Shannon Navigation that in-river works for the construction of the Killaloe Bypass bridge commence Monday 17 April and are expected to continue for several months until December.

The bridge is being constructed around 1km downstream of the existing Killaloe–Ballina bridge.

Plant and other equipment that will be operating on the navigation during these in-river works include the following:

  • Jack-up piling barge, 22m x 17m x 2.44m
  • Stabilising crane barge, 30m x 23m x 1.88m
  • Piling rig, 85t
  • Crawler crane, 130t
  • Tugboat/pusher boat Tiger 2
  • Dumb barge, 23m x 9m
  • Landing craft
  • Safety boat
  • Landing pontoon and gangways

Piling will commence on Tuesday 2 May with three bridge piers being constructed in the navigation by December, the cross-border body for Ireland’s inland waterways says.

A buoyed navigation channel has been provided for 100 metres either side of the in river works since Friday 14 April. The navigation channel will be to the west side of the barges/pontoons from Monday 17 April to Wednesday 31 May.

Masters of vessels are requested to proceed at slow speed, with additional caution in the vicinity of the works, and to follow the instructions of the safety boat crew.

Published in Inland Waterways

Waterways Ireland advises masters of vessels and waterways users on the Shannon Navigation that a series of events will take place in Killaloe next weekend (16-18 September) as part of the end-of-season LUA celebration of ‘wild water’ in the Co Clare village.

Friday 16 September will see the Lough Derg branch of the Inland Waterways Association of Ireland (IWAI) hold its end-of-season celebration with commodores John and Sandra Lefroy and Matt Daniels with guest of honour Mayor of Clare, Tony O’Brien. 
                                         
In addition, Norma Manly and band will be in concert at St Flannan’s Cathedral from 8pm.

On Saturday 17 September, there will be a presentation by Gary McMahon, director of the AKA Ilen project on sailing in Irish and international waters for over a century. This takes place at noon in St Flannan’s Cathedral.

It will be followed by a presentation by Martin Cooper on the cathedral’s distinctive bells at 3pm, honouring Bryan and Betty Brislane.

And at 8pm there will be a special concert — Killaloe: a musical celebration — featuring Mary Donahue, Paul Fitzpatrick and friends. Proceeds will go to the Lough Derg Coast Guard and Killaloe Fire and Rescue Services.

On Sunday 18 September, Caroline Rainsford will host a special hour-long session of tai chi by the waterside from 9am, free and suitable for all abilities.

At 11.30am, there will be an ecumenical service at St Flannan’s that will include a blessing of the waterways and environs, followed by a presentation to Sandra and John Lefroy of the famed steamboat Phoenix as well as a closing celebration hosted by the IWAI’s Lough Derg branch.

Throughout the weekend, St Flannan’s will also host a special art exhibition from local artist Trish Taylor Thompson on the theme of the waterways.

Meanwhile, Waterways Ireland advises masters of vessels that construction works have commenced on a new bridge across the Shannon Navigation around 1km downstream of the existing bridge in Killaloe.

A silt curtain has been installed in the navigation and construction works will be extending into the navigation over the next 12 months. Masters of vessels should proceed with additional caution in the vicinity of the construction works.

Published in Inland Waterways

The inland waterways will be celebrated at Killaloe next month, the quintessential waterways town on the River Shannon in Co.Clare.

Called ‘LUA’, it will be “a celebration of wild water at the ancient settlement of Killaloe, which is a gift of the Shannon, ” says Rev.Paul Fitzpatrick, Dean’s Vicar at St.Flannan’s Cathedral in Killaloe, who has designed the event “to explore our evolving engagement with wild water and how best to individually and collectively irrigate a more beneficial relationship with it, both culturally and environmentally.”

Rev Paul Fitzpatrick and members of his Killaloe congregationRev Paul Fitzpatrick and members of his Killaloe congregation

It will take place from Friday, September 16, through Saturday and Sunday, September 17 and 18, with an exhibition on the theme of waterways and the environment and a presentation by the Director of the AK ILEN project, Gary McMahon, about the restoration of Ireland’s last sailing schooner.

"Called ‘LUA’, it will be “a celebration of wild water at the ancient settlement of Killaloe"

Killaloe is “incredible with maritime history, rooted in the ancient and contemporary, revolving around the life and times of what is the treasure of the maritime and the inland waterways,” says Rev. Fitzpatrick, an enthusiastic boater on the Shannon himself.

Listen to him on the Podcast here

Published in Tom MacSweeney

BreakingNews.ie reports that a charity rower was left “shaken” after he was rescued from strong currents in the River Shannon at the Killaloe bridge.

Killaloe Coast Guard Unit were tasked at 2.40pm yesterday (Wednesday 25 September) to the scene where the rower had managed to secure his vessel to the navigation markers leading to the bridge.

The rescue team were with the rower within minutes and transferred him to safety while his vessel was taken under tow to the public slipway at Ballina.

BreakingNews.ie says the incident follows a “lucky escape” for three men last month whose lake boat collided with the same bridge.

Published in Rescue
Tagged under
Page 1 of 3

About Dublin Port 

Dublin Port is Ireland’s largest and busiest port with approximately 17,000 vessel movements per year. As well as being the country’s largest port, Dublin Port has the highest rate of growth and, in the seven years to 2019, total cargo volumes grew by 36.1%.

The vision of Dublin Port Company is to have the required capacity to service the needs of its customers and the wider economy safely, efficiently and sustainably. Dublin Port will integrate with the City by enhancing the natural and built environments. The Port is being developed in line with Masterplan 2040.

Dublin Port Company is currently investing about €277 million on its Alexandra Basin Redevelopment (ABR), which is due to be complete by 2021. The redevelopment will improve the port's capacity for large ships by deepening and lengthening 3km of its 7km of berths. The ABR is part of a €1bn capital programme up to 2028, which will also include initial work on the Dublin Port’s MP2 Project - a major capital development project proposal for works within the existing port lands in the northeastern part of the port.

Dublin Port has also recently secured planning approval for the development of the next phase of its inland port near Dublin Airport. The latest stage of the inland port will include a site with the capacity to store more than 2,000 shipping containers and infrastructures such as an ESB substation, an office building and gantry crane.

Dublin Port Company recently submitted a planning application for a €320 million project that aims to provide significant additional capacity at the facility within the port in order to cope with increases in trade up to 2040. The scheme will see a new roll-on/roll-off jetty built to handle ferries of up to 240 metres in length, as well as the redevelopment of an oil berth into a deep-water container berth.

Dublin Port FAQ

Dublin was little more than a monastic settlement until the Norse invasion in the 8th and 9th centuries when they selected the Liffey Estuary as their point of entry to the country as it provided relatively easy access to the central plains of Ireland. Trading with England and Europe followed which required port facilities, so the development of Dublin Port is inextricably linked to the development of Dublin City, so it is fair to say the origins of the Port go back over one thousand years. As a result, the modern organisation Dublin Port has a long and remarkable history, dating back over 300 years from 1707.

The original Port of Dublin was situated upriver, a few miles from its current location near the modern Civic Offices at Wood Quay and close to Christchurch Cathedral. The Port remained close to that area until the new Custom House opened in the 1790s. In medieval times Dublin shipped cattle hides to Britain and the continent, and the returning ships carried wine, pottery and other goods.

510 acres. The modern Dublin Port is located either side of the River Liffey, out to its mouth. On the north side of the river, the central part (205 hectares or 510 acres) of the Port lies at the end of East Wall and North Wall, from Alexandra Quay.

Dublin Port Company is a State-owned commercial company responsible for operating and developing Dublin Port.

Dublin Port Company is a self-financing, and profitable private limited company wholly-owned by the State, whose business is to manage Dublin Port, Ireland's premier Port. Established as a corporate entity in 1997, Dublin Port Company is responsible for the management, control, operation and development of the Port.

Captain William Bligh (of Mutiny of the Bounty fame) was a visitor to Dublin in 1800, and his visit to the capital had a lasting effect on the Port. Bligh's study of the currents in Dublin Bay provided the basis for the construction of the North Wall. This undertaking led to the growth of Bull Island to its present size.

Yes. Dublin Port is the largest freight and passenger port in Ireland. It handles almost 50% of all trade in the Republic of Ireland.

All cargo handling activities being carried out by private sector companies operating in intensely competitive markets within the Port. Dublin Port Company provides world-class facilities, services, accommodation and lands in the harbour for ships, goods and passengers.

Eamonn O'Reilly is the Dublin Port Chief Executive.

Capt. Michael McKenna is the Dublin Port Harbour Master

In 2019, 1,949,229 people came through the Port.

In 2019, there were 158 cruise liner visits.

In 2019, 9.4 million gross tonnes of exports were handled by Dublin Port.

In 2019, there were 7,898 ship arrivals.

In 2019, there was a gross tonnage of 38.1 million.

In 2019, there were 559,506 tourist vehicles.

There were 98,897 lorries in 2019

Boats can navigate the River Liffey into Dublin by using the navigational guidelines. Find the guidelines on this page here.

VHF channel 12. Commercial vessels using Dublin Port or Dun Laoghaire Port typically have a qualified pilot or certified master with proven local knowledge on board. They "listen out" on VHF channel 12 when in Dublin Port's jurisdiction.

A Dublin Bay webcam showing the south of the Bay at Dun Laoghaire and a distant view of Dublin Port Shipping is here
Dublin Port is creating a distributed museum on its lands in Dublin City.
 A Liffey Tolka Project cycle and pedestrian way is the key to link the elements of this distributed museum together.  The distributed museum starts at the Diving Bell and, over the course of 6.3km, will give Dubliners a real sense of the City, the Port and the Bay.  For visitors, it will be a unique eye-opening stroll and vista through and alongside one of Europe’s busiest ports:  Diving Bell along Sir John Rogerson’s Quay over the Samuel Beckett Bridge, past the Scherzer Bridge and down the North Wall Quay campshire to Berth 18 - 1.2 km.   Liffey Tolka Project - Tree-lined pedestrian and cycle route between the River Liffey and the Tolka Estuary - 1.4 km with a 300-metre spur along Alexandra Road to The Pumphouse (to be completed by Q1 2021) and another 200 metres to The Flour Mill.   Tolka Estuary Greenway - Construction of Phase 1 (1.9 km) starts in December 2020 and will be completed by Spring 2022.  Phase 2 (1.3 km) will be delivered within the following five years.  The Pumphouse is a heritage zone being created as part of the Alexandra Basin Redevelopment Project.  The first phase of 1.6 acres will be completed in early 2021 and will include historical port equipment and buildings and a large open space for exhibitions and performances.  It will be expanded in a subsequent phase to incorporate the Victorian Graving Dock No. 1 which will be excavated and revealed. 
 The largest component of the distributed museum will be The Flour Mill.  This involves the redevelopment of the former Odlums Flour Mill on Alexandra Road based on a masterplan completed by Grafton Architects to provide a mix of port operational uses, a National Maritime Archive, two 300 seat performance venues, working and studio spaces for artists and exhibition spaces.   The Flour Mill will be developed in stages over the remaining twenty years of Masterplan 2040 alongside major port infrastructure projects.

Source: Dublin Port Company ©Afloat 2020.