Stena Line has decreased the carbon emissions by 11% per tonne of cargo carried over each nautical mile, as well as achieving a reduction of 4% total ship emissions compared to pre-Covid operations.

The main contributor to the result is the significantly higher utilisation and thus efficiency of the company´s fleet with cargo during the latest years. In its roadmap to a net-zero future, Stena Line has set up a target to reduce total CO2 emissions from its vessels by 30% by 2030.

During port operations and lay times, Stena Line now uses 100% renewable electricity. The energy is used for shore power at 20% of Stena Line´s terminals while berthing, to load battery packages on-board and for electric vehicles onshore that are used during port operations. Furthermore, initiatives like prior access to e-trucks to Stena Line´s ferries and pilot projects to use recycled methanol from the steel industry as shipping fuel lay the foundation for further step-wise greening of the operations of Stena Line.

“At Stena Line we have a broad approach to sustainability, based on care – care for our customers, care for our resources and care for each other. As we strive to reduce energy consumption in all of our operations, I am proud that by introducing our new E-Flexer ferries in our route network, we made significant steps in further improving our overall efficiency during operations. But aside from technological and operational means, it is as important to work hard on structures and culture to become an even more sustainable company and contribute to our societal responsibilites”, says Niclas Mårtensson, CEO Stena Line.

Stena Line´s sustainability efforts are based on six dedicated Sustainable Development goals of the UN: Affordable and clean energy, responsible consumption and production, life below water, gender equality, reduced inequalities, good health and well-being.

Further highlights in Stena Line´s sustainability efforts during 2021 include:

  • A recycling rate of 42% of waste and a fallback of landfill waste to 2019 levels (24%), before plastic use increased for safety purposes
  • 50% female representation in Stena Line’s Group Management Team
  • Appointing the first female captain in Lynette Bryson, serving on Stena Aventurer on the key route Dublin-Holyhead
  • Recruiting the first Diversity and Inclusion Lead in Salem Yohannes, helping Stena Line to speed up the journey to equality and launch of a diversity and inclusion campaign
  • Introducing Maria Tornvall as new Head of Sustainability, committed to aligning Stena Line´s sustainable actions towards the ambitious targets
  • Improving employee indicators such as engagement, team efficiency, leadership, organisation and social work environment above benchmark and achievement of a positive net promoter score of 9 – meaning  employees would recommend Stena Line as an attractive workplace.
  • Reduction of sick leave average from 5,2% to 4,2%

“Stena Line has been a trailblazer for the industry when it comes to implementing sustainable technology, operations and structures, and we are aiming to retain our position as a leading company in this area. It is important to show and tell what we as company and people working at Stena Line can do to make a difference, to inspire and to motivate. Yes, the future is challenging on various levels, but with a clear roadmap towards a net-zero future and an even better workplace, defined steps how to reach the targets, and not the least the dedication of all of us, there are a lot of reasons for optimism”, says Maria Tornvall, Head of Sustainability at Stena Line.

To consult the ferry operator's sustainability report, this is available to download here.

Published in Stena Line
Tagged under

At the Port of Waterford today, Iarnród Eireann and XPO Logistics, a leading global provider of freight transportation solutions, launched a new rail freight service in each direction between the south-east port and Ballina, Co Mayo.

The new rail service begins weekly operations today, building to twice-weekly within eight weeks.

It will offer Irish industry a greener and more efficient mode of transporting freight between the West and southeast of the country. In addition the service sees the potential for over 5,000 truck movements a year to switch from road to rail, with a resulting reduction in road congestion, and 75% reduction in emissions per unit.

The new service comes as Iarnród Éireann is finalising a new national rail freight strategy to identify growth and investment opportunities to significantly grow rail freight operations.

Port of Waterford Chief Executive Frank Ronan said, “Port of Waterford welcomes the re-introduction of rail freight services to the Port at Belview. These trains, carrying container freight, will work very effectively with the Port's Lo-Lo shipping services to provide businesses in Ireland's West/North West with a compelling logistics solution to and from mainland Europe.

Minister for Transport, Eamon Ryan TD, welcomed the new service, saying: “The rail network has a critical role to play in transforming how we transport people and goods with a view to achieving net-zero emissions. This service offers a practical and sustainable option for businesses on both sides of the country who are looking to move goods for domestic and export markets. As we examine the potential to increase the use of the network for freight, it is fitting that this new service will offer an immediate solution for freight movement between these key locations.”

Minister of State for Transport & Logistics, Hildegarde Naughton TD said: “Ireland’s freight, logistics and distribution transport sector plays a critical role in our economy and this new service will sustainably connect businesses in the West of Ireland to the Port of Waterford and onwards to export markets. Our supply chains are resilient and by adding new rail transport offerings to industry, we can continue to support local communities and in turn, our climate objectives.”

Iarnród Éireann Chief Executive Jim Meade said, "We are entering a very exciting phase where rail freight can offer key solutions for the movement of freight as the country addresses both environmental and congestion challenges in this sector. We are currently finalising a very ambitious strategic plan for the growth of rail freight between key locations across the country. Today's announcement with XPO and Waterford Port demonstrates the viable opportunities that can be developed that will not just support industry and the logistics sector, but is also fully aligned with the country's climate action plan."

Dan Myers, managing director, transport – UK and Ireland, XPO Logistics said, “Climate change is a critical global challenge; the solutions will take a concerted effort, coordinated action and cooperation. Our collaborative, end-to-end service with Irish Rail — where XPO provides the booking of rail freight movements, drayage trucking of containers, and services such as cross-docking — is a double win. Our customers have new, eco-friendly transport options, and our planet wins as supply chains become greener. It’s another step in our collective journey to a carbon-neutral future.”

He added "Dublin's carbon emissions reductions and road and port congestion alleviation make this a worthwhile initiative. We wish XPO Logistics every success with this venture and look forward to working with them."

Iarnród Éireann is continuing to work with existing and potential new customers and Freight Forwarders, Ports and the Irish Exporters Association to identify opportunities and trends for rail freight development within the Irish and European market.

The new rail freight service between Ballina and Waterford is in addition to existing rail freight operations, which include:

-         Container traffic from Ballina to Dublin Port

-         Pulpwood from Ballina and Westport to Waterford Port

-         Zinc ore from Tara Mines in Navan to Dublin Port

Published in Irish Ports

#FerryNews - A Scandinavian ferry operating between Sweden and Denmark, the Stena Jutlandica has now completed its first month of operation as a battery hybrid vessel and the positive experiences from the first weeks of service have exceeded expectations.

“It's really exciting to be running with electrical power on the Stena Jutlandica. This project is an important part of our focused efforts to find ways of reducing our impact on the environment. As both the size and cost of batteries decrease, battery operation is becoming a very attractive alternative to traditional fuel for shipping as it should be possible to completely eliminate emissions in the future,” says Erik Lewenhaupt, Head of Sustainability at Stena Line.

The battery project is being carried out in steps. Step One, which is presently underway, is about switching to electrical operation to reduce the use of diesel generators, as well as for maneuvering and powering the bow thrusters when the ship is in port.

In Step Two, battery power will be connected to two of the four primary machines, which means that the Stena Jutlandica will be able to run on electrical power for about 10 nautical miles inside the archipelago out to Vinga Lighthouse (Gothenburg, Sweden).

During Step Three, all four primary machines will be connected to the batteries and the ship will be able to cover the 50 nautical miles between Sweden and Denmark solely on electrical power. A number of positive effects have already been noted after just one month.

“We've been able to significantly reduce our use of the diesel generators and now only need to use one instead of three. Another positive effect concerns safety. Having constant access to electricity, we minimize the risk for power outages”, says Johan Stranne, Senior Chief Engineer on the Stena Jutlandica.

In Step One alone, the environmental savings from using battery power for reduced generator usage and maneuvering in port amounts to approximately 500 tons of fuel saved and 1,500 tons of reduced CO2. This corresponds to the annual emissions from approximately 600 cars.

The rationale for execution in multiple steps is to enable testing and assessment while the project is underway. If the project is successful, battery power can be considered for other vessels within the Stena Line fleet. Work on Step Two has begun and the goal is for implementation within approximately three years.

The technical solutions in Step One have been developed by Stena Teknik in collaboration with the Callenberg Technology Group, with half of the funding for the project coming from the Swedish Transport Administration and the EU.

Published in Ferry

About Dublin Port 

Dublin Port is Ireland’s largest and busiest port with approximately 17,000 vessel movements per year. As well as being the country’s largest port, Dublin Port has the highest rate of growth and, in the seven years to 2019, total cargo volumes grew by 36.1%.

The vision of Dublin Port Company is to have the required capacity to service the needs of its customers and the wider economy safely, efficiently and sustainably. Dublin Port will integrate with the City by enhancing the natural and built environments. The Port is being developed in line with Masterplan 2040.

Dublin Port Company is currently investing about €277 million on its Alexandra Basin Redevelopment (ABR), which is due to be complete by 2021. The redevelopment will improve the port's capacity for large ships by deepening and lengthening 3km of its 7km of berths. The ABR is part of a €1bn capital programme up to 2028, which will also include initial work on the Dublin Port’s MP2 Project - a major capital development project proposal for works within the existing port lands in the northeastern part of the port.

Dublin Port has also recently secured planning approval for the development of the next phase of its inland port near Dublin Airport. The latest stage of the inland port will include a site with the capacity to store more than 2,000 shipping containers and infrastructures such as an ESB substation, an office building and gantry crane.

Dublin Port Company recently submitted a planning application for a €320 million project that aims to provide significant additional capacity at the facility within the port in order to cope with increases in trade up to 2040. The scheme will see a new roll-on/roll-off jetty built to handle ferries of up to 240 metres in length, as well as the redevelopment of an oil berth into a deep-water container berth.

Dublin Port FAQ

Dublin was little more than a monastic settlement until the Norse invasion in the 8th and 9th centuries when they selected the Liffey Estuary as their point of entry to the country as it provided relatively easy access to the central plains of Ireland. Trading with England and Europe followed which required port facilities, so the development of Dublin Port is inextricably linked to the development of Dublin City, so it is fair to say the origins of the Port go back over one thousand years. As a result, the modern organisation Dublin Port has a long and remarkable history, dating back over 300 years from 1707.

The original Port of Dublin was situated upriver, a few miles from its current location near the modern Civic Offices at Wood Quay and close to Christchurch Cathedral. The Port remained close to that area until the new Custom House opened in the 1790s. In medieval times Dublin shipped cattle hides to Britain and the continent, and the returning ships carried wine, pottery and other goods.

510 acres. The modern Dublin Port is located either side of the River Liffey, out to its mouth. On the north side of the river, the central part (205 hectares or 510 acres) of the Port lies at the end of East Wall and North Wall, from Alexandra Quay.

Dublin Port Company is a State-owned commercial company responsible for operating and developing Dublin Port.

Dublin Port Company is a self-financing, and profitable private limited company wholly-owned by the State, whose business is to manage Dublin Port, Ireland's premier Port. Established as a corporate entity in 1997, Dublin Port Company is responsible for the management, control, operation and development of the Port.

Captain William Bligh (of Mutiny of the Bounty fame) was a visitor to Dublin in 1800, and his visit to the capital had a lasting effect on the Port. Bligh's study of the currents in Dublin Bay provided the basis for the construction of the North Wall. This undertaking led to the growth of Bull Island to its present size.

Yes. Dublin Port is the largest freight and passenger port in Ireland. It handles almost 50% of all trade in the Republic of Ireland.

All cargo handling activities being carried out by private sector companies operating in intensely competitive markets within the Port. Dublin Port Company provides world-class facilities, services, accommodation and lands in the harbour for ships, goods and passengers.

Eamonn O'Reilly is the Dublin Port Chief Executive.

Capt. Michael McKenna is the Dublin Port Harbour Master

In 2019, 1,949,229 people came through the Port.

In 2019, there were 158 cruise liner visits.

In 2019, 9.4 million gross tonnes of exports were handled by Dublin Port.

In 2019, there were 7,898 ship arrivals.

In 2019, there was a gross tonnage of 38.1 million.

In 2019, there were 559,506 tourist vehicles.

There were 98,897 lorries in 2019

Boats can navigate the River Liffey into Dublin by using the navigational guidelines. Find the guidelines on this page here.

VHF channel 12. Commercial vessels using Dublin Port or Dun Laoghaire Port typically have a qualified pilot or certified master with proven local knowledge on board. They "listen out" on VHF channel 12 when in Dublin Port's jurisdiction.

A Dublin Bay webcam showing the south of the Bay at Dun Laoghaire and a distant view of Dublin Port Shipping is here
Dublin Port is creating a distributed museum on its lands in Dublin City.
 A Liffey Tolka Project cycle and pedestrian way is the key to link the elements of this distributed museum together.  The distributed museum starts at the Diving Bell and, over the course of 6.3km, will give Dubliners a real sense of the City, the Port and the Bay.  For visitors, it will be a unique eye-opening stroll and vista through and alongside one of Europe’s busiest ports:  Diving Bell along Sir John Rogerson’s Quay over the Samuel Beckett Bridge, past the Scherzer Bridge and down the North Wall Quay campshire to Berth 18 - 1.2 km.   Liffey Tolka Project - Tree-lined pedestrian and cycle route between the River Liffey and the Tolka Estuary - 1.4 km with a 300-metre spur along Alexandra Road to The Pumphouse (to be completed by Q1 2021) and another 200 metres to The Flour Mill.   Tolka Estuary Greenway - Construction of Phase 1 (1.9 km) starts in December 2020 and will be completed by Spring 2022.  Phase 2 (1.3 km) will be delivered within the following five years.  The Pumphouse is a heritage zone being created as part of the Alexandra Basin Redevelopment Project.  The first phase of 1.6 acres will be completed in early 2021 and will include historical port equipment and buildings and a large open space for exhibitions and performances.  It will be expanded in a subsequent phase to incorporate the Victorian Graving Dock No. 1 which will be excavated and revealed. 
 The largest component of the distributed museum will be The Flour Mill.  This involves the redevelopment of the former Odlums Flour Mill on Alexandra Road based on a masterplan completed by Grafton Architects to provide a mix of port operational uses, a National Maritime Archive, two 300 seat performance venues, working and studio spaces for artists and exhibition spaces.   The Flour Mill will be developed in stages over the remaining twenty years of Masterplan 2040 alongside major port infrastructure projects.

Source: Dublin Port Company ©Afloat 2020.