Waterways Ireland advises all masters of vessels and users of the Shannon Navigation that that the Spencer Harbour public jetty and amenity area, and the areas of Lough Allen immediately upstream and downstream of the harbour, will be closed from Monday 20 to Friday 24 May due to planned site preparation works for the construction of the new slipway.

The cross-border body of Ireland’s inland waterways regrets any inconvenience that this may cause and thanks its customers for their cooperation in relation to this matter.

Published in Inland Waterways

Waterways Ireland advises masters and owners of vessels on the Shannon Navigation that water levels in all areas north of Lough Ree are now at Ordinary Summer Level.

Water levels on the Shannon Navigation south of Lough Ree are approaching Ordinary Summer Level.

Levels are expected to continue to lower in the coming weeks, the cross-border body for Ireland’s inland waterways adds.

Masters of vessels, particularly those with deep drafts, are advised to navigate with additional caution and to remain within the navigation at all times.

Published in Inland Waterways

Waterways Ireland wishes advises masters of vessels on and users of the Shannon Navigation that the Office of Public Works’ hydrometric section is holding a water flow measurement regatta next Wednesday 15 May.

The event will take place from 8am to 3pm for a distance of 200 metres from the floating pontoon located at the Red Bridge on the River Inny near Ballymahon in Co Longford.

Masters of Vessels and users of the Inny River are requested to proceed with additional caution during the event, the cross-border body for Ireland’s inland waterways adds.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on and users of the Shannon Navigation that in-river works for the construction of a wastewater treatment plant outfall pipe will take place from Tuesday 7 May to Friday 7 June downstream of Killaloe/Ballina.

Two isolated danger buoys will mark the extremity of the in-river works which will extend from the Ballina side into the river for around 70 metres.

Masters of vessels are requested to proceed at slow speed (5 knots, no wash) with additional caution in the vicinity of the works and to follow the instructions of the safety boat crew.

Elsewhere, boaters on the Shannon-Erne Waterway are advised that the waterfront jetty in Leitrim village is now owned and managed by Waterways Ireland, the cross-border body for Ireland’s inland waterways.

This jetty is located upstream of the slipway on the northern side of the waterway. The Shannon Navigation Bye Laws apply to this jetty as of 17 April 2023.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on and users of the Shannon Navigation that the closure of Tarmonbarry Bridge will be extended until at least Monday 27 May.

This further delay is due to additional repair works requiring specialist components being manufactured and delivered from international suppliers.

The cross-border body for Ireland’s inland waterways says the parts required are essential to the safe operation of the bridge.

A diversion route remains available via the Camlin River with additional staff being deployed to Clondra Lock to aid vessel movements along the Camlin.

Waterways Ireland says it regrets any inconvenience that this may cause and thanks its customers for their cooperation in relation to this matter.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on and users of the Shannon Navigation that the Gaelforce Great River Swim will take place between Tarmonbarry and Ballyleague next month.

Around 500 swimmers will participate in the swim event in Lanesborough on Saturday 18 May.

The Shannon Navigation between Tarmonbarry lock and Ballyleague bridge will be closed on the day between 9am and 2pm. Tarmonbarry lock and Cloondara Canal lock will also be closed and vessels will be prohibited from proceeding upstream from Ballyleague bridge during thus time.

A series of large bright green and red buoys branded with Gaelforce will be positioned along the swim route on the evening of Friday 17 May and will be removed after the swim on Saturday 18 May, the cross-border body for Ireland’s inland waterways says.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on and users of the Shannon Navigation that the lifting bridge at Tarmonbarry in Co Roscommon will now reopen on Friday 3 May.

This extension of the bridge’s closure since February is a result of additional repair works required following a bridge strike.

The cross-border body for Ireland’s inland waterways says it apologises for extending this closure “but the additional work is essential to ensure the bridge is safely operational in advance of the bank holiday weekend”.

A diversion route remains available via the Camlin River.

Published in Inland Waterways

Waterways Ireland advises masters of vessels on the Shannon Navigation that in-river works for the construction of the Killaloe Bypass upper bridge superstructure are progressing as planned and will continue until October 2024.

As previously reported on Afloat.ie, the bridge is being constructed around 1km downstream of the current Killaloe–Ballina bridge.

A buoyed navigational channel continues to be provided for 100 metres either side of the in-river works.

The following plant and equipment will be operating on or overhead the navigation during the upper bridge works:

  • 600t crawler crane set up on the east shore
  • Stabilising crane barge (30m x 23m x 1.88m)
  • 100t crawler crane
  • Tugboat/pusher boat
  • Dumb barge (23m x 9m) and mobile elevated work platforms
  • Safety boat
  • Landing pontoon and gangways

From next Tuesday 2 to Friday 19 April, the final steel girders will be lifted into position in the central spans of the bridge.

This is a heavy lift operation and deemed high-risk work, requiring calm waters for operation of mobile elevated work platforms (MEWP) on barges.

Masters of vessels are requested to proceed at slow speed (5 knots, no wash) with additional caution in the vicinity of the works, and to follow the instructions of the safety boat crew as there are hazards such as bridge piers, steel piles and mooring lines to navigate.

The cross-border body for Ireland’s inland waterways thanks its customers for their cooperation in relation to these works.

Published in Inland Waterways

Waterways Ireland advises masters of vessels that the winter mooring period will end this Easter Sunday, 31 March, on the Shannon Navigation and Shannon-Erne Waterway.

Shannon Navigation Bye-law No. 17(3) will apply from 31 March, such that vessels should not berth in the same harbour for longer than the statutory period of five consecutive days nor more than a total of seven days in any one month.

Services were reconnected to Waterways Ireland harbours and jetties from Friday 15 March, the cross-border body for Ireland’s inland waterways adds.

Published in Inland Waterways

Waterways Ireland advises all masters of vessels on and users of the Shannon Navigation that Battlebridge Lock and the harbour areas immediately upstream and downstream in Battlebridge, Co Leitrim will be closed from this Wednesday 27 to Friday 29 March due to planned diving inspections in the area.

The cross-border body for Ireland’s inland waterways says it regrets any inconvenience that this may cause and thanks its customers for their cooperation.

Published in Inland Waterways
Page 1 of 19

About Safehaven Marine 

Safehaven Marine are designers and builders of FRP Pilot boats, Patrol boats, Crew transfer vessels, Hydrographic survey catamarans, Naval & Military craft and unique custom private motor yachts. All our vessels are built to the highest standards of strength & engineering and are renowned worldwide for their exceptional sea-keeping abilities, we set a new World long-range speed record in 2017 with our own vessel and crew. Established in 1996 we have built over 138 vessels supplied to 27 countries worldwide with over 40 pilot vessels in operation globally, and have become leaders in our field.

Based in Youghal, Co Cork Ireland, Safehaven manufacture our vessels from two modern factories, with all design work carried out in house, and built with our own experienced team of engineers, carpenters, electricians, shipwrights and laminators.

Always at the forefront of new technology and designs we continuously develop our range and push the frontiers of design: In 2020 we aim to set a UIM Transatlantic World record with our unique (patent applied for) new 22m high-speed vessel XSV20

Interceptor 42 pilot boat

The Pilot 42 model built by Safehaven Marine has been delivered to ports worldwide and has proved to be a superb sea boat performing admirably in pilotage operations with all owners extolling its virtues of seakeeping, strength and stability.

L.O.A. (Length overall) 13.2m

L.W.L. (Length along waterline) 11.5m

Length moulded (GRP hull only) 12.7

Beam Moulded (GRP only ex fender) 4.0m

Beam overall (Including fenders) 4.4m

Draft (Depth of hull below waterline) 1.35m

Displacement Lightship 14,500kg

Fully loaded 16,000kg

Fuel capacity 1600 litres

Water capacity 110 litres

Crew capacity 5 persons

Engines Volvo D9 425hp

Gearboxes ZF325

Subdivision 4 x separate watertight compartments

Crew capacity 1-2 crew plus 3- 4 pilots

Classification PRS

Speed 23.5kts fully loaded