#FoynesJettyProject - The Limerick Leader writes that the name of the successful contractor who will carry out a multi-million upgrade of the east jetty at Foynes will be announced shortly by Shannon Foynes Port Company.

The project, which the SFPC says will cost in excess of €10m, will be the largest single investment at Foynes port since the extension of the west jetty in 1999.

The project is part of the port company's masterplan, Vision 2041, in which it anticipated that the east jetty project would deliver some 150 jobs at the construction stage.

The work on the east jetty is expected to be completed in two phases. To read more about both stage of the project and more click HERE.

 

Published in Shannon Estuary

Dun Laoghaire Baths Renovation

Afloat has been reporting on the new plans for the publically owned Dun Laoghaire Baths site located at the back of the East Pier since 2011 when plans for its development first went on display by Dun Laoghaire Rathdown County Council. 

Foreshore consent was applied for in 2013.

Last used 30 years ago as the 'Rainbow Rapids' before falling into dereliction – the new site does not include a public pool.

The refurbished Dun Laoghaire Baths include the existing Baths Pavilion for use as artist workspaces, a gallery café and for the provision of public toilet facilities. 

Work finally got underway at Dún Laoghaire on the €9 million redevelopments of the old Dún Laoghaire Baths site in June 2018 under a contract with SIAC-Mantovani.

The works have removed dilapidated structures to the rear of the Pavilion to permit the creation of a new route and landscaping that will connect the walkway at Newtownsmith to both the East Pier and the Peoples Park. 

Original saltwater pools have been filled in and new enhanced facilities for swimming and greater access to the water’s edge by means of a short jetty have also been provided.

The works included the delivery of rock armour to protect the new buildings from storm damage especially during easterly gales. 

It hasn't all been plain sailing during the construction phase with plastic fibres used in construction washing into the sea in November 2018

Work continues on the project in Spring 2020 with the new pier structure clearly visible from the shoreline.

A plinth at the end of the pier will be used to mount a statue of Roger Casement, a former Sandycove resident and Irish nationalist.