#ferries - In the UK at the Merseyside shipbuilder Cammell Laird which has completed building its 1393rd vessel, the previously reported £10m freight-ferry Red Kestrel for Isle of Wight ferry operator Red Funnel.

The Red Kestrel, a new ro-ro freight-only vessel, sailed away from Cammell Laird’s famous River Mersey shipyard following a nine-month build programme.

In total the project used 45 British supply chain businesses and generated 3000 man hours of work for Cammell Laird's apprentices. Cammell Laird further employed 200 direct workers, 200 sub-contractors and 10 apprentices on the contract.

Tony Graham, Cammell Laird’s Chief Operating Officer, said: “Cammell Laird would like to thank Red Funnel for placing its trust in us to build this wonderful state-of-the-art ferry, drawing on all our marine engineering expertise. Completing this ship sends a very strong message to the global maritime industry about Cammell Laird’s ferry building capabilities after we won the contract against international competition. We are proud to see the Red Kestrel join a collection of ferries that Cammell Laird has built in recent years in addition to the large number of drydockings and repairs we do each year in the ferry sector.

“Shipbuilding is back in a serious way on the Mersey and it has been brilliant to see the Red Kestrel being built alongside the iconic RRS Sir David Attenborough, which is the largest commercial vessel built in Britain for a generation. Cammell Laird sees a big market in ferry repair, conversion and new build and we will be showcasing our work on the Red Kestrel at the Nor Shipping trade fair in Oslo later this year. It is tremendous to see more ship owners and ferry operators choosing to build in the UK, this is very much in line with the Government’s National Shipbuilding Strategy which aims to create a renaissance in British shipbuilding as a major job and wealth creator.”

Fran Collins, CEO of Red Funnel, said, “We are delighted to see the Red Kestrel begin its journey to Southampton for her naming ceremony and her life on the Solent. The addition of a new ship is always an exciting time for everyone in the company. We’re thrilled that not only will Red Kestrel increase our total capacity and enhance convenience for our cross-Solent customers but we also take tremendous pride in supporting the revival of world-class shipbuilding in this country. It’s a very special feeling for all of us and we’ve been in very good hands with Cammell Laird. Cammell Laird has been a brilliant partner and we are very grateful for all their tremendous work.”

The Red Kestrel will operate between Southampton and Isle of Wight. The vessel will officially join the fleet on arrival in Southampton, and enter service in May, following trials and its official naming ceremony. The Red Kestrel is Red Funnel's first dedicated RoRo freight ship since the company’s inception almost 200 years ago. As a freight vessel she is limited to 12 passengers and constructed specifically to provide additional year-round freight capacity for Red Funnel’s Southampton-East Cowes route, which currently handles 53% of all freight movements across the Solent. Red Kestrel is due to enter service in May 2019, with the current ferry timetable to be updated to accommodate the vessel.

At 74m in length, she will provide 265 lane metres of roll-on/roll-off freight capacity. To minimise the environmental footprint, the hull shape has been designed specifically to reduce wash and a propulsion package has been selected to make her highly fuel efficient whilst meeting the latest Tier III emission regulations. The use of proven azimuth thrusters supplied by Rolls Royce, will also make the ship very manoeuvrable.  The crossing time of 55-60 minutes will be identical to Red Funnel’s existing Raptor class ro-pax ships and she will use the same berths in Southampton and East Cowes.

Published in Ferry

Dun Laoghaire Baths Renovation

Afloat has been reporting on the new plans for the publically owned Dun Laoghaire Baths site located at the back of the East Pier since 2011 when plans for its development first went on display by Dun Laoghaire Rathdown County Council. 

Foreshore consent was applied for in 2013.

Last used 30 years ago as the 'Rainbow Rapids' before falling into dereliction – the new site does not include a public pool.

The refurbished Dun Laoghaire Baths include the existing Baths Pavilion for use as artist workspaces, a gallery café and for the provision of public toilet facilities. 

Work finally got underway at Dún Laoghaire on the €9 million redevelopments of the old Dún Laoghaire Baths site in June 2018 under a contract with SIAC-Mantovani.

The works have removed dilapidated structures to the rear of the Pavilion to permit the creation of a new route and landscaping that will connect the walkway at Newtownsmith to both the East Pier and the Peoples Park. 

Original saltwater pools have been filled in and new enhanced facilities for swimming and greater access to the water’s edge by means of a short jetty have also been provided.

The works included the delivery of rock armour to protect the new buildings from storm damage especially during easterly gales. 

It hasn't all been plain sailing during the construction phase with plastic fibres used in construction washing into the sea in November 2018

Work continues on the project in Spring 2020 with the new pier structure clearly visible from the shoreline.

A plinth at the end of the pier will be used to mount a statue of Roger Casement, a former Sandycove resident and Irish nationalist.