Plans to refurbish the Port of Holyhead's Breakwater amid concerns it could fail within the next 15 years has led to a consultation launched.

Investigations of the structure have identified a need for a large scale refurbishment of the Breakwater to ensure that it can continue to receive about 70% of all ferry vehicle movement between Ireland and Wales and the North West.

Since its completion in 1873, the Breakwater has been subject to considerable wave action, which has led to the movement and erosion (as Afloat reported) of the rubble mound, that supports the structures wall.

Over the coming years it is anticipated that the level of the mound will become so low that the footing of the vertical walls will be at risk of being undermined.

"Investigations of the structure have predicted that the Breakwater could fail within the next 15 years meaning a permanent solution must be found," a Stena Line Ports spokesperson said.

More from North Wales Pioneer here.

Published in News Update

#HMScaroline - An historic ship with a wartime past that is a modern day Belfast tourist attraction has had its future secured thanks to a major programme of innovative repairs, safety upgrades and improvements.

As the Belfast Telegraph writes, HMS Caroline, the only survivor of the First World War Battle of Jutland, is now nearly ship-shape and Bristol fashion again and ready to reopen to the public, who visited it in their thousands last year.

The ship underwent extensive repairs over the winter and engineers came up with an ingenious solution to the problem of how to make it even safer for visitors.

The National Museum of the Royal Navy said it was one of the most innovative engineering projects seen in Ireland, and it is nearing completion at Alexandra Dock in Belfast.

The ship was fully restored and opened to the public in May 2016 with £15,086,100 backing from the Heritage Lottery Fund and £4,518,000 support from Tourism NI.

But repairs were needed to the hull and they have been carried out by Harland and Wolff Heavy Industries.

 At the same time a hugely-complex permanent mooring system to make the ship safe for the public and also to protect it from lateral movements as it floats on the rising and falling tides is now close to completion. For more on the return of the floating tourist attraction, click here.

Published in Historic Boats

#TALL SHIPS - The Irish Whale and Dolphin Group (IWDG) has secured three-quarters of the funding it required to refit its research vessel Celtic Mist.

According to The Irish Times, the Clare Local Development Company has approved the allocation of a €48,000 grant towards the refurbishment of the ketch.

The work will be carried out by Cathal Blunnie and several sub-contractors, and involves stripping down the main cabin and removing the bath and shower to increase space for crew berths.

While the ship's clock will be retained, the ship’s wheel in the main cabin will be removed and presented to the Haughey family as a gesture of appreciation.

As previously reported on Afloat.ie, the 52-foot yacht - which was gifted by the Haughey family to the IWDG to assist in its marine wildlife conservation work - entered dry dock last November in preparation for the refit work, after relocating to its new berth at Kilrush, Co Clare in July.

This followed its last jaunt at sea in its former guise, completing a leg of the Tall Ships Races from Waterford to Greenock in Scotland.

The cost of refurbishing the yacht for research and training purposes is expected to top €60,000, with an annual running cost of some €20,000, for which the IWDG is seeking ongoing financial assistance.

The group aims to get the Celtic Mist back at sea before the summer.

Published in Tall Ships
#TALL SHIPS - Not only has the Celtic Mist finally been lifted into dry dock for refurbishing this week, but the Irish Independent reports that day trips will be offered on the yacht when it returns to the water next summer.
As previously reported on Afloat.ie, the one-time personal yacht of the late Taoiseach Charles Haughey is being repurposed as a research vessel by new owners the Irish Whale and Dolphin Group (IWDG) at a cost of some €60,000.
In an effort to help fund the 52-foot ketch's refit bill and its estimated €20,000-per-year running costs, members of the public who pay €50 for a 'Celtic Mist Certificate' will be entitled to a day's sailing on board the newly retitled RV Celtic Mist.
IWDG co-ordinator Dr Simon Berrow said: "We've a lot of work to carry out on the yacht before we can take it out for research," IWDG co-ordinator Simon Berrow told the Independent. "We are confident that we can raise the money to run it."

#TALL SHIPS - Not only has the Celtic Mist finally been lifted into dry dock for refurbishing this week, but the Irish Independent reports that day trips will be offered on the yacht when it returns to the water next summer.

As previously reported on Afloat.ie, the one-time personal yacht of the late Taoiseach Charles Haughey is being repurposed as a research vessel by new owners the Irish Whale and Dolphin Group (IWDG) at a cost of some €60,000.

In an effort to help fund the 52-foot ketch's refit bill and its estimated €20,000-per-year running costs, members of the public who pay €50 for a 'Celtic Mist Certificate' will be entitled to a day's sailing on board the newly retitled RV Celtic Mist.

IWDG co-ordinator Dr Simon Berrow said: "We've a lot of work to carry out on the yacht before we can take it out for research," IWDG co-ordinator Simon Berrow told the Independent. "We are confident that we can raise the money to run it."

Here's a link to a TV3 clip

Published in Tall Ships
#TALL SHIPS - RTÉ News reports that the Celtic Mist is finally in dry dock for refurbishment to begin its new life as a maritime research vessel.
As previously reported on Afloat.ie, the 52-foot yacht - which was gifted by the Haughey family to the Irish Whale and Dolphin Group (IWDG) to assist in its marine wildlife conservation work - relocated to its new berth at Kilrush, Co Clare in July.
This followed its last jaunt at sea earlier this year, completing a leg of the Tall Ships Races from Waterford to Greenock.
The cost of refurbishing the yacht for research and training purposes is expected to top €60,000, with an annual running cost of some €20,000, for which the IWDG is seeking ongoing financial assistance.
The group aims to get the Celtic Mist back at sea before next summer.

#TALL SHIPS - RTÉ News reports that the Celtic Mist is finally in dry dock for refurbishment to begin its new life as a maritime research vessel.

As previously reported on Afloat.ie, the 52-foot yacht - which was gifted by the Haughey family to the Irish Whale and Dolphin Group (IWDG) to assist in its marine wildlife conservation work - relocated to its new berth at Kilrush, Co Clare in July.

This followed its last jaunt at sea earlier this year, completing a leg of the Tall Ships Races from Waterford to Greenock.

The cost of refurbishing the yacht for research and training purposes is expected to top €60,000, with an annual running cost of some €20,000, for which the IWDG is seeking ongoing financial assistance.

The group aims to get the Celtic Mist back at sea before next summer.

Published in Tall Ships
Northern Ireland Water has announced that some of its reservoirs will be closed to angling temporarily from next January to facilitate refurbishment work.
The water levels on the reservoirs in the DCAL Public Angling Estate work be lowered on a phased basis from next year by Northern Ireland Water.
Ahead of that work, fisheries staff will be reducing fish stocks in the interest of welfare.
The fisheries will be closed from the start date of the works until the refurbishment work is completed, water levels restored and stocking re-commenced stocking, which could take up to a year.
Anglers will be notified of the details of the temporary closures of Public Angling Estate waters on the Department’s website
Full details will be available online for anglers at www.nidirect.gov.uk/angling.
Closure dates (subject to change) are listed below:
Portavoe - January 2012
Copeland - January 2012
Lough Mourne - April 2012
Lower South Woodburn - November 2012
Middle South Woodburn - March 2013
Upper South Woodburn - August 2013
North Woodburn - January 2014

Northern Ireland Water has announced that some of its reservoirs will be closed to angling temporarily from next January to facilitate refurbishment work. 

The water levels on the reservoirs in the DCAL Public Angling Estate work be lowered on a phased basis from next year by Northern Ireland Water.

Ahead of that work, fisheries staff will be reducing fish stocks in the interest of welfare. 

The fisheries will be closed from the start date of the works until the refurbishment work is completed, water levels restored and stocking re-commenced stocking, which could take up to a year.

Anglers will be notified of the details of the temporary closures of Public Angling Estate waters on the Department’s website 

Full details will be available online for anglers at www.nidirect.gov.uk/angling.

Closure dates (subject to change) are listed below:

Portavoe - January 2012

Copeland - January 2012

Lough Mourne - April 2012

Lower South Woodburn - November 2012

Middle South Woodburn - March 2013

Upper South Woodburn - August 2013

North Woodburn - January 2014

Published in Angling
Kinsale Yacht Club (KYC) held an information meeting last Tuesday to discuss the situation of its aging clubhouse ahead of a planned EGM later this month.
Structural problems were previously discussed at a club meeting last November, at which a number of options were presented.
These included undertaking a complete refurbishment of the building, and the option of moving the club to a new green field site on the other side of the River Bandon.
Tuesday's meeting at KYC saw presentations from an engineer, an architect, a quantity surveyor and an expert financial advisor based on these options, in order to evaluate the best choice for the club going forward - namely the first option of refurbishing.
The club committee will propose a motion to adopt its recommendation to move ahead with refurbishment plans at the EGM, scheduled for Tuesday 24 May at 8pm.

Kinsale Yacht Club (KYC) held an information meeting last Tuesday to discuss the situation of its aging clubhouse ahead of a planned EGM later this month.

Structural problems were previously discussed at a club meeting last November, at which a number of options were presented. 

These included undertaking a complete refurbishment of the building, and the option of moving the club to a new green field site on the other side of the River Bandon.

Tuesday's meeting at KYC saw presentations from an engineer, an architect, a quantity surveyor and an expert financial advisor based on these options, in order to evaluate the best choice for the club going forward - namely the first option of refurbishing.

The club committee will propose a motion to adopt its recommendation to move ahead with refurbishment plans at the EGM, scheduled for Tuesday 24 May at 8pm.

Published in Kinsale

National Watersports Campus, Dun Laoghaire

Dun Laoghaire Harbour Stakeholders combined forces in 2019 to promote a project to improve the Harbour’s infrastructure resulting in improved access, job creation and greater tourism potential. 

A grant application to government made by Dun Laoghaire Rathdown County Council (DLRCoCo) assisted by stakeholders was successful with the announcement of a €400k feasibility study grant from the Large Scale Sport Infrastructure Fund (LSSIF) in January 2020.

It meant plans for the €8m National Watersports Campus at Dun Laoghaire Harbour got the green light from Government and came a step closer to reality.

The project recognises deficits in the current set up in the harbour, proposing the construction of an all-tide publicly-accessible slipway (none currently in the Greater Dublin Area) as well as a marine services facility, providing a much-needed home for the supporting industry. 

The campus also seeks to provide a marketing framework to make boating more accessible to the general public.

The benefits of such an increase might be obvious for the Dun Laoghaire waterfront but there are other spin-offs for the harbour town in the creation of the sort of jobs that cannot be shipped abroad.

Centre for Community Watersports activity and public slipway

  • High-Performance coaching centre
  • Flexible Event Space for hosting national and international events
  • Multipurpose Building
  • Campus Marketing and Promotional Centre
  • Accommodation for Irish Sailing and Irish Underwater Council
  • Shared NGB Facility
  • Education Centre for schools, community groups and clubs
  • Proposed site – Carlisle Pier

Watersports Campus FAQs

Similar to the National Sports Campus in Abbotstown, the watersports campus will provide quality, public, recreational and high-performance facilities for the many watersports participants. The Campus will considerably enhance the services currently provided by more than 30 clubs and activity centres to over 50,000 annual users of the harbour.

The passing of control of the harbour to DLRCC, the public appetite for a community benefitting project and the capital funding for sports infrastructure in the Project 2040 National Plan have aligned to create an opportunity to deliver this proposal.

Dun Laoghaire Rathdown County Council (DLRCC) and the Irish Sailing Association (Irish Sailing) are the project leads, endorsed by the National Governing Bodies of other Irish watersports and clubs and activity providers.

The National Sports Policy, published in 2018, established the Large Scale Sport Infrastructure Fund (LSSIF) to provide Exchequer support for sports facility projects. In some cases, these may be projects where the primary objective will be to increase active participation in sport. In other cases, these may be venues where the focus is more related to high-performance sport.

Government has allocated at least €100m over the term to 2027 to successful applicant projects.

The Watersports Campus was one of seven successful applicants for Stream 1 funding allowing planning to commence on the project design and feasibility. €442,000 has been granted in this phase.

NThe project will provide for a municipally-owned public access facility to include a small craft slipway that is accessible at all stages of the tide (currently none in public ownership in the greater Dublin area), storage and lock-up resources, watersports event management space, a high-performance centre and NGB accommodation.

The project aims to enhance the profile of Dun Laoghaire as a major international venue for maritime events, shows and conferences. Establish Dun Laoghaire as the 'go-to place' for anything marine – generating revenues Create employment in the county - attract businesses, visitors and events. Grow the market for watersports Promote the services of activity providers to the public. Complement the plan to develop Dun Laoghaire as a 'destination.'

As of January 1 2021, The Department of Transport, Tourism and Sport has approved the applicant project and DLRCC are expected to appoint a team to further advance the project.