Menu

Ireland's sailing, boating & maritime magazine

Displaying items by tag: New Dual Fuel ferry

At a Scottish shioyard is where a massively delayed new Isle of Arran ferry has taken a huge stride towards completion.

The MV Glen Sannox, reports the Herald, is the first of two dual fuel vessels being built at Ferguson Marine Ltd., is currently four years behind schedule, being at the heart of the £230 million ferries fiasco.

Now the boat has been moved to dry dock in Greenock to undergo remedial works including replacement of the bulbous bow, paint repair and removal of marine growth from the vessel hull.

The ferry has been sitting in the water at Ferguson Marine's Port Glasgow facility since 2017.

Work had been called off due to coronavirus, but crews began returning in June. It is not yet clear how much of a delay the pandemic has had on the Glen Sannox or the as-yet unamed second vessel - Hull 802.

For more on this development click here.

Published in Ferry

Featured Sailing School

INSS sidebutton

Featured Clubs

dbsc mainbutton
Howth Yacht Club
Kinsale Yacht Club
National Yacht Club
Royal Cork Yacht Club
Royal Irish Yacht club
Royal Saint George Yacht Club

Featured Brokers

leinster sidebutton

Featured Webcams

Featured Associations

ISA sidebutton
ICRA
isora sidebutton

Featured Marinas

dlmarina sidebutton

Featured Chandleries

CHMarine Afloat logo
https://afloat.ie/resources/marine-industry-news/viking-marine

Featured Sailmakers

northsails sidebutton
uksails sidebutton
watson sidebutton

Featured Blogs

W M Nixon - Sailing on Saturday
podcast sidebutton
BSB sidebutton
wavelengths sidebutton
 

Please show your support for Afloat by donating