This morning's report into the sinking of Asgard II will indicate that collision with an underwater object such as a submerged container was the likely cause of the ship sinking. The final report of the Marine Casualty Investigation Board into the loss of the brigantine sailing ship STV "Asgard II " on 11th September 2008 will be published this morning.

On 10th September 2008 the STV "Asgard II" departed Dournenez, France bound for La Rochelle, France with 5 crew and 20 trainee crew onboard. At approximately 01:00 hrs GMT on 11th September 2008 when off St. Nazaire in the Bay of Biscay water ingress was observed in the Trainee Mess. At 01:05 hrs a Pan Pan message was broadcast. At about 01:15 hrs a Mayday Relay message was received by French Search and Rescue (French SAR) as the water in the Trainee Mess continued rising rapidly. The crew attempted to pump the flood water without success.

The ship was abandoned by liferaft at approximately 01:50 hrs. Two French lifeboats rescued all 25 persons from the liferafts.

During the abandonment the floor of one of the three liferafts launched failed and the persons onboard were successfully transferred to the other liferafts. No loss of life occurred and there were no injuries reported.

Click this link for all Afloat's coverage of Asgard II's sinking, and the plans to raise, dive and replace her

Raise the Asgard - Afloat's 2008 online petition
Published in Asgard II
The Marine Casualty Investigation Board (MCIB) has published its Report of Investigation into the Loss of a Crewmember Overboard from the MFV "Alma Amy" on 17th October 2007. The report found that on Wednesday 17th October 2007 Mr. Marijus Rudakov fell overboard from the MFV "Alma Amy" and drowned in an area off the South East coast of Ireland known as "The Smalls" approximately 50 miles southeast of the Wexford coast. (As shown in Appendix 8.5).
The cause of the death was determined by post mortem examination as being due to cardiorespiratory arrest secondary to drowning. The full report is available for download below.
Published in MCIB
The Marine Casualty Investigation Board has issued a report of Investigation into the loss of a crewmember overboard from the MFV "MDAC" on 15th July 2009. The report says while shooting a string of lobster pots on the morning of 15th July 2009 from the MFV "MDAC" off Fenit, Co. Kerry, Mr. Patrick Egan's leg became caught in a bight of rope and he was pulled over the side. Mr. Denis Williams, the Skipper, stopped the engine and took all way off the vessel. He then hauled Mr. Egan back on board the boat but was unable to resuscitate him. Mr. Egan died due to acute cardio-respiratory failure and drowning. The full MCIB report is available for download below.
Published in MCIB

The Marine Casualty investigation board has issued its Report of Investigation into the grounding and subsequent foundering of an Emerald Star Line Caprice 8, a Charter boat, The boat ran aground on rocks in the vicinity of Mountaineer Rock, off Ryan's Point on Lough Derg, Co. Tipperary last October 9th. The four persons on board were taken off by the Portumna Fire and Rescue RIB and ferried across the lake to Williamstown Harbour. The vessel was noted to have been severely holed. The vessel was pulled off the rocks and subsequently sank while under tow. There were no fatalities and no pollution associated with this incident. A copy of the report can be downloaded below.

Published in MCIB

The Marine Casualty Investigation Board has advised reports into the "Skellig Light II", Claddaghduff and "Ikom K" accidents will be released later today. Check back here for full details as we have them.

Published in MCIB

An investigation into the sinking of the FV "Strath Marie" off Inishowen Head, Co. Donegal on 14th March 2008 has found no direct cause for the loss of both lives. The FV "Strath Marie" left Bunagee Pier, Culdaff, Co. Donegal to lift strings of pots. Crewmembers Mr. Francis McDaid and Mr. Daniel McDaid were on board.

The weather forecast was for south to southwest Force 3 or 4 with good visibility and slight to moderate sea state. The reported weather conditions on the day were better than the forecast. At 17.17 hrs. on 14th of March 2008 a "999" call was made as the "Strath Marie" was overdue.

At 18.13 hrs. on 14th March 2008 the first casualty was recovered from the water and at 20.38 hrs. the second casualty was recovered. Both men were brought to Altnagelvin Hospital in Derry where they were later pronounced dead.

Parts of the fishing vessel were later recovered and examined along with other evidence to try and establish the cause of the loss of the FV "Strath Marie". The full report is downloadable below.

 

Published in MCIB

A Marine Casualty Investigation Board (MCIB) report into the death of Mr. Alain Adler after the six metre boat in he which he travelling capsized from a pier in West Cork in 2008 has found there was no single cause for this casualty. It was the accumulation of several poor decisions which resulted in the capsize of the vessel and related fatality. The post mortem found that Mr. Alder died as a result of acute cardio-respiratory failure and drowning associated with hypothermia.

In the early hours of 5th December 2008, ten people set off from Colla Pier near Schull, Co. Cork in an open boat (with sealed deck) powered by a 30 HP outboard engine to spend the weekend on Coney Island, which lies about one kilometre off the coast of Cork, in the south west of Ireland.

Shortly afterwards the boat capsized resulting in the death of Mr. Alain Adler.  The post mortem found that Mr. Adler died as a result of acute cardio-respiratory failure and drowning associated with hypothermia.

The report also concludes that although several members of the group were familiar with boats and the dangers of the sea, none wore the lifejackets/PFD's provided.

The full MCIB report is downloadable below.mcib

Published in MCIB
Page 16 of 16

About Dublin Port 

Dublin Port is Ireland’s largest and busiest port with approximately 17,000 vessel movements per year. As well as being the country’s largest port, Dublin Port has the highest rate of growth and, in the seven years to 2019, total cargo volumes grew by 36.1%.

The vision of Dublin Port Company is to have the required capacity to service the needs of its customers and the wider economy safely, efficiently and sustainably. Dublin Port will integrate with the City by enhancing the natural and built environments. The Port is being developed in line with Masterplan 2040.

Dublin Port Company is currently investing about €277 million on its Alexandra Basin Redevelopment (ABR), which is due to be complete by 2021. The redevelopment will improve the port's capacity for large ships by deepening and lengthening 3km of its 7km of berths. The ABR is part of a €1bn capital programme up to 2028, which will also include initial work on the Dublin Port’s MP2 Project - a major capital development project proposal for works within the existing port lands in the northeastern part of the port.

Dublin Port has also recently secured planning approval for the development of the next phase of its inland port near Dublin Airport. The latest stage of the inland port will include a site with the capacity to store more than 2,000 shipping containers and infrastructures such as an ESB substation, an office building and gantry crane.

Dublin Port Company recently submitted a planning application for a €320 million project that aims to provide significant additional capacity at the facility within the port in order to cope with increases in trade up to 2040. The scheme will see a new roll-on/roll-off jetty built to handle ferries of up to 240 metres in length, as well as the redevelopment of an oil berth into a deep-water container berth.

Dublin Port FAQ

Dublin was little more than a monastic settlement until the Norse invasion in the 8th and 9th centuries when they selected the Liffey Estuary as their point of entry to the country as it provided relatively easy access to the central plains of Ireland. Trading with England and Europe followed which required port facilities, so the development of Dublin Port is inextricably linked to the development of Dublin City, so it is fair to say the origins of the Port go back over one thousand years. As a result, the modern organisation Dublin Port has a long and remarkable history, dating back over 300 years from 1707.

The original Port of Dublin was situated upriver, a few miles from its current location near the modern Civic Offices at Wood Quay and close to Christchurch Cathedral. The Port remained close to that area until the new Custom House opened in the 1790s. In medieval times Dublin shipped cattle hides to Britain and the continent, and the returning ships carried wine, pottery and other goods.

510 acres. The modern Dublin Port is located either side of the River Liffey, out to its mouth. On the north side of the river, the central part (205 hectares or 510 acres) of the Port lies at the end of East Wall and North Wall, from Alexandra Quay.

Dublin Port Company is a State-owned commercial company responsible for operating and developing Dublin Port.

Dublin Port Company is a self-financing, and profitable private limited company wholly-owned by the State, whose business is to manage Dublin Port, Ireland's premier Port. Established as a corporate entity in 1997, Dublin Port Company is responsible for the management, control, operation and development of the Port.

Captain William Bligh (of Mutiny of the Bounty fame) was a visitor to Dublin in 1800, and his visit to the capital had a lasting effect on the Port. Bligh's study of the currents in Dublin Bay provided the basis for the construction of the North Wall. This undertaking led to the growth of Bull Island to its present size.

Yes. Dublin Port is the largest freight and passenger port in Ireland. It handles almost 50% of all trade in the Republic of Ireland.

All cargo handling activities being carried out by private sector companies operating in intensely competitive markets within the Port. Dublin Port Company provides world-class facilities, services, accommodation and lands in the harbour for ships, goods and passengers.

Eamonn O'Reilly is the Dublin Port Chief Executive.

Capt. Michael McKenna is the Dublin Port Harbour Master

In 2019, 1,949,229 people came through the Port.

In 2019, there were 158 cruise liner visits.

In 2019, 9.4 million gross tonnes of exports were handled by Dublin Port.

In 2019, there were 7,898 ship arrivals.

In 2019, there was a gross tonnage of 38.1 million.

In 2019, there were 559,506 tourist vehicles.

There were 98,897 lorries in 2019

Boats can navigate the River Liffey into Dublin by using the navigational guidelines. Find the guidelines on this page here.

VHF channel 12. Commercial vessels using Dublin Port or Dun Laoghaire Port typically have a qualified pilot or certified master with proven local knowledge on board. They "listen out" on VHF channel 12 when in Dublin Port's jurisdiction.

A Dublin Bay webcam showing the south of the Bay at Dun Laoghaire and a distant view of Dublin Port Shipping is here
Dublin Port is creating a distributed museum on its lands in Dublin City.
 A Liffey Tolka Project cycle and pedestrian way is the key to link the elements of this distributed museum together.  The distributed museum starts at the Diving Bell and, over the course of 6.3km, will give Dubliners a real sense of the City, the Port and the Bay.  For visitors, it will be a unique eye-opening stroll and vista through and alongside one of Europe’s busiest ports:  Diving Bell along Sir John Rogerson’s Quay over the Samuel Beckett Bridge, past the Scherzer Bridge and down the North Wall Quay campshire to Berth 18 - 1.2 km.   Liffey Tolka Project - Tree-lined pedestrian and cycle route between the River Liffey and the Tolka Estuary - 1.4 km with a 300-metre spur along Alexandra Road to The Pumphouse (to be completed by Q1 2021) and another 200 metres to The Flour Mill.   Tolka Estuary Greenway - Construction of Phase 1 (1.9 km) starts in December 2020 and will be completed by Spring 2022.  Phase 2 (1.3 km) will be delivered within the following five years.  The Pumphouse is a heritage zone being created as part of the Alexandra Basin Redevelopment Project.  The first phase of 1.6 acres will be completed in early 2021 and will include historical port equipment and buildings and a large open space for exhibitions and performances.  It will be expanded in a subsequent phase to incorporate the Victorian Graving Dock No. 1 which will be excavated and revealed. 
 The largest component of the distributed museum will be The Flour Mill.  This involves the redevelopment of the former Odlums Flour Mill on Alexandra Road based on a masterplan completed by Grafton Architects to provide a mix of port operational uses, a National Maritime Archive, two 300 seat performance venues, working and studio spaces for artists and exhibition spaces.   The Flour Mill will be developed in stages over the remaining twenty years of Masterplan 2040 alongside major port infrastructure projects.

Source: Dublin Port Company ©Afloat 2020.