#HSSberth – The disused Stena HSS berth at Dun Laoghaire Harbour is to be dismantled and removed in a process taking up to 10 weeks to complete, writes Jehan Ashmore.
Planning permission was granted to Stena by Dun Laoghaire-Rathdown County Council to dismantle berth No. 5 at St. Micheal’s Pier from where the final HSS Stena Explorer sailing to Holyhead took place in September 2014.
The operator having consolidated existing services on the Dublin Port route to the Welsh port that began in 1995.
Work at No. 5 berth is where the specialist docking infrastructure designed only for Stena HSS 1500 class fast-ferries, is to involve the removal of the linkspan, gangway and associated equipment.
A tug, MTS Valour is to begin towage of a barge from Stranraer, Scotland to Dun Laoghaire where the HSS related structures are to be loaded on board.
Coincidentally, Stranraer is also where Stena operated the HSS Stena Voyager in tandem with a pair of ferries on the Belfast route until switching Scottish ferryport to Cairnryan in 2011.
Also as part of the works in Dun Laoghaire (see Notice to Mariners No. 9) will be the removal of the pontoon at No 4 which is the adjacent berth on St. Micheals Pier. This berth-linkspan was last used by the smaller fast-ferry, Stena Lynx III until 2011.
Afloat.ie awaits a response from Dun Laoghaire Harbour Company to finally confirm proposals to restore seasonal-only ferry services to Holyhead, having begun a tendering process in February 2015.
Only in recent months saw the retail letting opportunity of the former ferry terminal and now the project to remove ferry-related infrastructure from the port.