Iarnród Éireann has signed a contract with BAM for the extension and upgrade of Berth 3 at Rosslare Europort, with construction scheduled to commence before the end of November.
The development will enable the Co Wexford port to accommodate longer, more efficient ferries and provide shore power infrastructure to reduce emissions from vessels while berthed.
The works form part of GREEN DRIFT, a €38.5 million partnership between Iarnród Éireann and Dunkirk-Port, co-funded by the European Union through its Connecting Europe Facility.
The Rosslare works include extending Berth 3, upgrading quayside infrastructure and operational areas, and installing an onshore power supply.
The investment will also increase berthing flexibility and future capacity at the south-east port.
Growing Continental Ferry Capacity
The development follows continued investment in direct maritime services between Ireland and mainland Europe.
Minister of State with responsibility for ports, Seán Canney, welcomed the contract signing, highlighting Rosslare's significant growth since Brexit.
“This additional berth capacity will help accommodate larger and more efficient vessels,” he said.
Mary Considine, Chief Executive of Iarnród Éireann, said the works would support the port's continued growth and carbon reduction ambitions.
She added that Rosslare's masterplan works and port digitisation were largely complete, with a planning decision on the proposed Offshore Renewable Energy Hub expected imminently.
John Lucy, Director of Civils at BAM Ireland, said the investment would strengthen Ireland's connectivity with mainland Europe and support the transition to a lower-carbon future.
Shore power installation works at Dunkirk-Port are expected to commence in the fourth quarter of 2027, with the overall GREEN DRIFT project scheduled for completion in the third quarter of 2028.