Dublin City Council is proposing a mammoth 9km sewage outfall pipe to help make Dublin Bay cleaner - at a cost of €220m.
Herald.ie reports that the 5m-wide pipe - longer than the Dublin Port Tunnel - would dump effluent from the Ringsend treatment plant far offshore, thereby avoiding pollution in the bay and sensitive areas such as Bull Island, which recently lost its EU Blue Flag status for Dollymount Strand.
Plans for the project, which DCC head of waste Pat Cronin described as the "greenest and most economic solution" will be open to public consultation in the near future, with a timetable for completion by 2015.
The pipeline and redeveloped treatment plant will be funded via the Department of the Environment's water services investment programme.

Dublin City Council is proposing a mammoth 9km sewage outfall pipe to help make Dublin Bay cleaner - at a cost of €220m.

Herald.ie reports that the 5m-wide pipe - longer than the Dublin Port Tunnel - would dump effluent from the Ringsend treatment plant far offshore, thereby avoiding pollution in the bay and sensitive areas such as Bull Island, which recently lost its EU Blue Flag status for Dollymount Strand.

Plans for the project, which DCC head of waste Pat Cronin described as the "greenest and most economic solution" will be open to public consultation in the near future, with a timetable for completion by 2015.

The pipeline and redeveloped treatment plant will be funded via the Department of the Environment's water services investment programme.

Published in Dublin Bay

Shannon Foynes Port Information

Shannon Foynes Port (SFPC) are investing in an unprecedented expansion at its general cargo terminal, Foynes, adding over two-thirds the size of its existing area. In the latest phase of a €64 million investment programme, SFPC is investing over €20 million in enabling works alone to convert 83 acres on the east side of the existing port into a landbank for marine-related industry, port-centric logistics and associated infrastructure. The project, which will be developed on a phased basis over the next five years, will require the biggest infrastructure works programme ever undertaken at the port, with the entire 83 acre landbank having to be raised by 4.4 metres. The programme will also require the provision of new internal roads and multiple bridge access as well as roundabout access.