Dublin-based Irish Commercial Charter Boats has played a key marine operations role in a record-breaking 1.8-kilometre cable duct installation for ScottishPower Renewables' East Anglia TWO offshore wind farm off Suffolk.
Dublin-based Irish Commercial Charter Boats (ICCB), headed by Eoin Grimes, has helped deliver a record-breaking offshore engineering operation involving two cable ducts almost 1.8 kilometres long for the East Anglia TWO wind farm off the English coast.
Grimes confirmed to Afloat.ie that ICCB was the marine contractor for the project, which ScottishPower Renewables says established a world record for the longest continuous single sections of extruded polyethylene ducting.
The ducts, each 800 millimetres in diameter and measuring approximately 1,793 metres in length, provide protected routes for the high-voltage export cables that will connect the wind farm to the shore.
Long Haul – Two continuous polyethylene ducts, each measuring approximately 1,793 metres, were installed beneath the Suffolk coastline as part of the £4 billion East Anglia TWO wind farm development. Photo: ICCB
Irish Marine Expertise in Major Offshore Operation
ICCB says it carried out all marine operations for OCU Group and Peter McCormack & Sons Limited, with a range of specialist vessels and contractors involved in the operation.
Photographs supplied directly to Afloat.ie by ICCB show a jack-up platform and support craft working alongside a long duct section extending across the water.
ICCB thanked Eoin Grimes, Tony Lock, Red7Marine, Carmet Tug Company, Thamescraft, Atlantic Towage, Norfolk Marine and SEP Hydrographic for their contributions.
Record-Breaking Cable Landfall
According to ScottishPower Renewables' announcement on 15 October, the ducts were installed using horizontal directional drilling beneath the Suffolk coastline and seabed, avoiding excavation across beaches and sensitive coastal habitats.
The developer says the combination of duct length and diameter makes this the largest electricity transmission landfall of its kind in the UK. The ducts were manufactured in continuous lengths by Pipelife in Norway and towed to Thorpeness in Suffolk.
The £4 billion East Anglia TWO wind farm will have a capacity of up to 960MW and is planned to operate from late 2028. Its first export cable is expected to be installed in summer 2027.
Irish Workboat Investment
ICCB's involvement follows earlier investment in specialist workboats for marine construction and offshore energy operations.
In January 2021, Afloat covered the company's commissioning of a purpose-built 12-metre landing craft, designed by Chartwell Marine for construction at Arklow Marine Services in County Wicklow.
The vessel was intended for offshore surveys, cable landing assistance and transport of personnel and supplies, illustrating the growing role of specialist Irish marine operators in offshore energy projects.