Menu

Ireland's sailing, boating & maritime magazine

Displaying items by tag: Technical issues

Stena Line’s Rosslare-Fishguard route, which was abandoned altogether for nearly six weeks, is still facing difficulties maintaining its southern corridor service between the Irish and Welsh ports.

As the Irish Independent reports, maintenance work at the Welsh port's linkspan berth has meant that the ropax Stena Nordica, which was announced as the “permanent” ferry on the Rosslare-Fishguard route last year, is unable to berth at the port at the moment.

In the meantime, Afloat adds that the ‘Nordica’ is running Dublin-Holyhead sailings, allowing the route’s routine ferries to go for an annual overhaul. The service on the St. George’s Channel was suspended for a number of weeks while the ferry operator carried out a reshuffle, which culminated in a return for the 1981-built Stena Europe. The veteran vessel, which had operated on the route for 21 years after replacing cruiseferry Koningin Beatrix in March 2002, served the Ireland-Wales route up until last July.

There were also mechanical issues, which meant that the suspension of the Rosslare-Fishguard crossing went on for nearly six weeks while the ageing ferry went for repairs at Cammell Laird on Merseyside. On completion of works at the facility’s Tranmere Wet Basin, Afloat tracked the ferry to nearby Liverpool Docks where it remained for short period.

Stena Europe, however, was eventually able to resume service last month. Among recent passengers including those on 'foot' were enthusiastic Welsh rugby fans that travelled the Irish Sea route to enjoy the Wexford pubs for their Six Nations clash with Ireland.

The resumption of the service is welcomed by many; however, there have again been a number of issues that have resulted in major delays and the cancellation of some sailings.

More from the newspaper here on the route operated by the long-serving Stena Europe as seen above in 2010 with a previous livery scheme. 

Published in Stena Line

A Clydeside shipyard has new technical problems including issues with 125 miles of cables are posing a further threat to a project to deliver one of the vessels at the centre of Scotland's ferry fiasco.

New nationalised Ferguson Marine analysis reveals that there remains a concern that the number of faults outstanding are a risk to the acceptance of the two vessels currently languishing at their shipyard.

There had been past concerns that a spiralling catalogue of faults with vessels to serious shipyard concerns over whether they will ever see service.

In May, internal documents from nationalised shipyard firm Ferguson Marine admitted a serious risk that minister-controlled ferry owners and procurers Caledonian Maritime Assets Limited may not accept the vessels for the ferry operator CalMac’s lifeline services to Scotland’s island communities. Those concerns remain.

Officially, Glen Sannox and Hull 802, which are due to serve the Clyde and Hebrides ferry network will be delayed until at least next year – over five years later than planned while costs have at least doubled from £97m to £250m.

But a July CMAL update raised further concerns about delivery, saying that a Ferguson Marine project report from May "did not consider the significant threats posed by the continued risk of late able installation".

It said that consideration is only given to the reinstatement of nearly 17 miles of cables removed from Glen Sannox in February.

But it said "no consideration" was given to the main body of cable installation that extended ship-wide totalling 125 miles.

The Herald has much more here on the challenges of the project. 

Published in Shipyards
Tagged under

As an island economy, a healthy maritime sector is key to our national competitiveness. Virtually all our imports and exports pass through Irish ports.

Ireland is dependent on ports and shipping services to transport goods and 90% of our trade is moved though Irish ports. Shipping and maritime transport services make a significant contribution to Ireland’s ocean economy, with the sector generating €2.3 billion in turnover and employing over 5,000 people in 2018.

Ireland’s maritime industry continues to grow and progress each year with Irish ports and shipping companies making significant investments. The ports sector in Ireland is currently undergoing a number of expansions and developments with Dublin Port’s Alexandra Basin development, the development of Ringaskiddy in Cork by Port of Cork and the development of Shannon Foynes Port. Along with these major investments, shipping companies are also investing heavily in new tonnage, with Irish Ferries, CLdN and Stena leading new build programmes.

These pages cover the following sectoral areas: shipowners, harbour authorities, shipbrokers, freight forwarders and contractors, cruise liner operators, port users, seamen, merchants, academic institutions, shipyards and repair facilities, naval architects, navy and defence personnel.

Our pages are covering some of the most notable arrivals around our coast and reporting too on port development and shipping news.

This section of the site deals with Port and Shipping News on our largest ports Dublin Port, Port of Cork, the Shannon Estuary, Galway Harbour and Belfast Lough.

A recent study carried out for the Irish Ports Association (IPA) totalled 75.7 billion during 2004 and their net economic impact was some 5.5 billion supporting around 57, 500 full time employees.

Liam Lacey, Director of the Marine Institute’s Irish Maritime Development Office (IMDO) said, “The Irish maritime industry can look to the future with confidence. It has shown itself to be resilient and agile in responding to challenges. Over the past decade, it has had to respond to the challenges of the financial crisis of 2008, the uncertainty surrounding Brexit and recent challenges. Ireland’s maritime sector has continued to underpin our economy by maintaining vital shipping links for both trade and tourism.”