#MarineNotice - Marine Notice No 46 of 2016 advises that piling works were set to commence at Howth Fishery Harbour Centre, weather permitting, on or around this past Monday 21 November.

The works involve the installation of 3 No. circular steel piles and the subsequent installation of a floating pontoon at the trawler dock (Western Basin) at latitude 53°23'32” N and longitude 6°4’6” W.

The works are being advanced by a marine contractor working from a jack-up barge 18m x 18m in size, using heavy civil engineering plant and machinery, work vessels and platforms. Divers will be employed onsite to install anodes to the piles.

For safety reasons, mariners are requested to proceed slowly and with caution in the trawler dock and to give the works a wide berth. Wave wash from vessels should be avoided.

These works are expected to be ongoing until the end of December 2016, weather permitting.

Published in News Update
MacDara Conroy

About The Author

MacDara Conroy

Email The Author

MacDara Conroy is a contributor covering all things on the water, from boating and wildlife to science and business

We've got a favour to ask

More people are reading Afloat.ie than ever thanks to the power of the internet but we're in stormy seas because advertising revenues across the media are falling fast. Unlike many news sites, we haven't put up a paywall because we want to keep our marine journalism open.

Afloat.ie is Ireland's only full-time marine journalism team and it takes time, money and hard work to produce our content.

So you can see why we need to ask for your help.

If everyone chipped in, we can enhance our coverage and our future would be more secure. You can help us through a small donation. Thank you.

Direct Donation to Afloat button