EirGrid is urging coastal communities and marine stakeholders to submit their views on proposed offshore cable infrastructure and associated electricity grid connections in Cork and Wexford before the public consultation closes on 8 December.
The 12-week consultation, launched in September, focuses on infrastructure required to connect future offshore wind generation from Tonn Nua, the first maritime area identified under the Government’s South Coast Designated Maritime Area Plan.
Options include cable landfall zones, offshore transmission corridors, offshore substations, grid connection locations and onshore cable routes.
EirGrid says the infrastructure will enable approximately 900MW of offshore renewable energy to be connected to the national grid, which it estimates is enough to power almost one million homes.
As Afloat reported in October, EirGrid has completed its 2026 marine and coastal survey campaign, covering 2,337km of maritime survey work.
Community Consultation: EirGrid has been engaging with coastal communities and marine stakeholders on emerging infrastructure options for offshore wind electricity transmission in Cork and Wexford.
Online Consultation Event on Thursday
A public information webinar is scheduled for Thursday, 26 November, from 7pm to 8pm.
Sinéad Dooley, EirGrid’s head of public engagement, encouraged interested parties to review the proposals and submit their views.
“Local knowledge is an important part of how we develop infrastructure projects, and every submission received will be carefully considered alongside technical and environmental assessments,” she said.
Consultation documents, webinar registration and submission details are available on EirGrid’s South Coast Offshore project website.